Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
4 | 7 | 4.00 | 0.00 | N/A |
County(s) | IL Project # | Airport | Sponsor | City |
---|---|---|---|---|
|
DEC 4822 | Decatur | Decatur Park District | Decatur |
Contract Specifics |
---|
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting. |
42 Calendar Days |
Previously advertised on January 19, 2024 (Item 09A). |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
AR150530 | L SUM | TRAFFIC MAINTENANCE | Base items | 1.000 | |||
AR152540 | SQ YD | SOIL STABILIZATION FABRIC | Base items | 1,602.000 | |||
AR209604 | SQ YD | CRUSHED AGG. BASE COURSE - 4" | Base items | 1,602.000 | |||
AR209606 | SQ YD | CRUSHED AGG. BASE COURSE - 6" | Base items | 24.000 | |||
AR501508 | SQ YD | 8" PCC PAVEMENT | Base items | 1,602.000 | |||
AR501530 | EACH | PCC TEST BATCH | Base items | 1.000 | |||
AR501605 | SQ FT | 5" PCC SIDEWALK | Base items | 216.000 | |||
AR501690 | SQ FT | PCC SIDEWALK REMOVAL | Base items | 216.000 | |||
AR501905 | SQ YD | REMOVE PAVEMENT | Base items | 1,602.000 | |||
AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 498.000 | |||
AR751411 | EACH | INLET-TYPE A | Base items | 1.000 | |||
AR751900 | EACH | REMOVE INLET | Base items | 1.000 | |||
AR751927 | EACH | REPLACE FRAME & GRATE | Base items | 1.000 | |||
AR754924 | FOOT | REPLACE COMB CURB & GUTTER | Base items | 45.000 | |||
AS152540 | SQ YD | SOIL STABILIZATION FABRIC | Additive 1 | 194.000 | |||
AS209604 | SQ YD | CRUSHED AGG. BASE COURSE - 4" | Additive 1 | 194.000 | |||
AS501508 | SQ YD | 8" PCC PAVEMENT | Additive 1 | 194.000 | |||
AS501905 | SQ YD | REMOVE PAVEMENT | Additive 1 | 194.000 | |||
AT152540 | SQ YD | SOIL STABILIZATION FABRIC | Additive 2 | 178.000 | |||
AT209604 | SQ YD | CRUSHED AGGREGATE BASE COURSE-4" | Additive 2 | 178.000 | |||
AT501508 | SQ YD | 8" PCC PAVEMENT | Additive 2 | 178.000 | |||
AT501905 | SQ YD | REMOVE PAVEMENT | Additive 2 | 178.000 | |||
No More Pay Items |