Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
1 | 1 | 0.00 | 0.00 | N/A |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
40 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200100 | CU YD | EARTH EXCAVATION | Base items | 1,822.000 | |||
20201200 | CU YD | REMOVAL AND DISPOSAL OF UNSUITABLE MATERIAL | Base items | 182.000 | |||
21001000 | SQ YD | GEOTECHNICAL FABRIC FOR GROUND STABILIZATION | Base items | 547.000 | |||
30300001 | CU YD | AGGREGATE SUBGRADE IMPROVEMENT | Base items | 547.000 | |||
31101400 | SQ YD | SUBBASE GRANULAR MATERIAL, TYPE B 6" | Base items | 10,935.000 | |||
40600275 | POUND | BITUMINOUS MATERIALS (PRIME COAT) | Base items | 24,603.000 | |||
40600290 | POUND | BITUMINOUS MATERIALS (TACK COAT) | Base items | 3,612.000 | |||
40603085 | TON | HOT-MIX ASPHALT BINDER COURSE, IL-19.0, N70 | Base items | 1,837.000 | |||
40604062 | TON | HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "D", N70 | Base items | 1,134.000 | |||
42000300 | SQ YD | PORTLAND CEMENT CONCRETE PAVEMENT 8" | Base items | 540.000 | |||
42001300 | SQ YD | PROTECTIVE COAT | Base items | 540.000 | |||
44000100 | SQ YD | PAVEMENT REMOVAL | Base items | 10,935.000 | |||
44000155 | SQ YD | HOT-MIX ASPHALT SURFACE REMOVAL, 1 1/2" | Base items | 2,560.000 | |||
44201765 | SQ YD | CLASS D PATCHES, TYPE II, 10 INCH | Base items | 50.000 | |||
44201769 | SQ YD | CLASS D PATCHES, TYPE III, 10 INCH | Base items | 50.000 | |||
66900200 | CU YD | NON-SPECIAL WASTE DISPOSAL | Base items | 430.000 | |||
66900530 | EACH | SOIL DISPOSAL ANALYSIS | Base items | 1.000 | |||
66901001 | L SUM | REGULATED SUBSTANCES PRE-CONSTRUCTION PLAN | Base items | 1.000 | |||
66901003 | L SUM | REGULATED SUBSTANCES FINAL CONSTRUCTION REPORT | Base items | 1.000 | |||
66901006 | CAL DA | REGULATED SUBSTANCES MONITORING | Base items | 3.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
78000200 | FOOT | THERMOPLASTIC PAVEMENT MARKING - LINE 4" | Base items | 600.000 | |||
X5537800 | FOOT | STORM SEWERS TO BE CLEANED 12" | Base items | 400.000 | |||
X6700407 | CAL MO | ENGINEER'S FIELD OFFICE, TYPE A (D1) | Base items | 12.000 | |||
Z0013798 | L SUM | CONSTRUCTION LAYOUT | Base items | 1.000 | |||
Z0018400 | EACH | DRAINAGE STRUCTURES TO BE ADJUSTED | Base items | 5.000 | |||
Z0018500 | EACH | DRAINAGE STRUCTURES TO BE CLEANED | Base items | 6.000 | |||
No More Pay Items |