Home > Notice of Letting > Contract Detail

November 07, 2025 Letting 12:00 PM
078-78B42

Bulletin Description

Installation of culvert liners at various locations along I-57 in District 9 (SN 091-7066, 091-7071, 091-7072, 091-7073 and 091-7077).
Region District DBE % VBP % Federal Project #
5 9 0.00 0.00 N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Union
  • FAI 57
  • I-57
  • (91-3,91-3-1,91-4)CLV-1
  • C-99-085-25
  • 9-00860-0010
  • 9-00860-0020
  • 9-00860-0030
  • 9-00860-0040
  • 9-00860-0050
Contract Specifics
35 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (3 Submitted / 3 Answered ) Questions not accepted as of October 28, 2025 04:30 PM.

  • Would Geocast or Shotcrete be an acceptable alternative liner in lieu of the Geopolymer?
    Only materials satisfying the special provision for spray applied pipe liners are acceptable. (10/23/2025)

  • Will the Illinois Department of Transportation consider allowing the use of a Profile Wall HDPE Pipe Liner meeting the requirements of ASTM F894 as an alternate to the specified Spray-Applied Pipe Liner (77”) for Item X5430477? Profile Wall HDPE Pipe is identified in IDOT Standard Specifications Section 1040.04(c) as an approved material for relining applications and has been successfully installed under state-maintained roadways in the past.
    The project should be bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications available online. The Contractor may submit a Value Engineering proposal, if they are the low bidder, after the award of the contract. (10/23/2025)

  • Will the Illinois Department of Transportation consider allowing the use of a Solid Wall HDPE Pipe Liner meeting the requirements of AASHTO M326 as an alternate to the specified Spray-Applied Pipe Liner (60”) for Item X5430460? Solid Wall HDPE Pipe is identified in IDOT Standard Specifications Section 1040.04(c) as an approved material for relining applications and has been successfully installed under state-maintained roadways in the past.
    The project should be bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications available online. The Contractor may submit a Value Engineering proposal, if they are the low bidder, after the award of the contract. (10/23/2025)

Authorized Bidders

  • 5306 Samron Midwest Contracting, Inc.
    PO Box 1555
    Murphysboro, IL 62966
    Phone: (618) 687-5500 Fax: (618) 684-9341 Email: info@samron.com
    $1,423,408.85 is within a reasonable approximation of the Estimate

  • 5978 Temple & Temple Excavating and Paving Inc.
    1367 S. State Road 60
    Salem, IN 47167
    Phone: (812) 883-6644 Fax: No Record Email: jasonn@templeandtemple.com
    $1,424,221.00

Non Bidders

  • 0737 CSD Environmental Services, Inc.
    (Pending Authorization)
    9979 Palm Road
    Glenarm, IL 62536
    Phone: (217) 522-4085 Fax: (217) 522-4087 Email: frank@csdenviro.com

Pay Item # UOM Description Type Quantity Unit Price
20100500 ACRE TREE REMOVAL, ACRES Base items 1.000
54390310 FOOT INSERTION CULVERT LINER 60" Base items 802.000
54390330 FOOT INSERTION CULVERT LINER 72" Base items 303.000
63301210 FOOT REMOVE AND REERECT STEEL PLATE BEAM GUARDRAIL, TYPE A Base items 360.000
67100100 L SUM MOBILIZATION Base items 1.000
70100800 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701401 Base items 1.000
70100825 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701456 Base items 1.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 84.000
X5430460 FOOT SPRAY-APPLIED PIPE LINER, 60" Base items 203.000
X5430477 FOOT SPRAY-APPLIED PIPE LINER, 77" Base items 479.000
No More Pay Items