Home > Notice of Letting > Contract Detail

November 07, 2025 Letting 12:00 PM
04A-LK016

Bulletin Description

Replace Automated Weather Observation System (AWOS)
Region District DBE % VBP % Federal Project #
1 1 0.00 0.00
County(s) IL Project # Airport Sponsor City
  • McHenry
3CK 5001 Lake in the Hills Village of Lake in the Hills Lake in the Hills
Contract Specifics
The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting.
30 Calendar Days
No More Contract Specifics

Ask Subscribe Questions and Answers (2 Submitted / 2 Answered ) Questions not accepted as of October 28, 2025 04:30 PM.

  • Will any of the approx. 200 cyds of sand for the "borrow excavation" to bring the site up 6 feet need to be contractor provided? If so, do you have a quantity?
    Borrow excavation shall be provided by the contractor using offsite borrow material for the construction of AWOS foundation embankment as noted in Section 152-1.1. Please note that there is no reference to sand as borrow excavation material in the plans or special provisions. Approximately 300 cubic yards of borrow excavation will be needed. As indicated in the plans (please refer to Proposed Improvements – 1 (Sheet 6), AWOS Notes 5), borrow excavation to raise existing ground to new ground elevation shall be incidental to AR152411 Unclassified Excavation. (10/29/2025)

  • Can the DBE requirement for this project be reduced?
    The DBE goal will remain 5.0% unless modified via addendum. (10/14/2025)

Authorized Bidders

  • 3011 J. Ranck Electric, Inc.
    1993 Gover Parkway
    MT. Pleasant, MI 48858
    Phone: (989) 775-7393 Fax: (989) 775-7393 Email: ajranck@jranck.com
    $538,000.00 is within a reasonable approximation of the Estimate

  • 2475 Hecker and Company, Inc.
    250 Industrial Lane
    Wheeling, IL 60090
    Phone: (847) 459-9222 Fax: (847) 459-9250 Email: dan@heckerco.com
    $563,555.00

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
AR125565 EACH SPLICE CAN Base items 3.000
AR150520 L SUM MOBILIZATION Base items 1.000
AR152411 L SUM UNCLASSIFIED EXCAVATION Base items 1.000
AR152540 SQ YD SOIL STABILIZATION FABRIC Base items 100.000
AR156510 FOOT SILT FENCE Base items 550.000
AR209608 SQ YD CRUSHED AGG. BASE COURSE - 8" Base items 100.000
AR800015 L SUM REMOVE AWOS EQUIPMENT AND FOUNDATIONS Base items 1.000
AR800016 L SUM INSTALL TYPE III AWOS Base items 1.000
AR800158 FOOT 2-1/C #6 XLP-USE, 1-1/C #6 GND IN 2" UD Base items 2,140.000
No More Pay Items