| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 4 | 7 | 4.00 | 0.00 | XKMC(318) |
| County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
|---|---|---|---|---|---|
|
|
|
|
|
|
| Contract Specifics |
|---|
| 45 Working Days |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| 20400800 | CU YD | FURNISHED EXCAVATION | Base items | 75.000 | |||
| 25000300 | ACRE | SEEDING, CLASS 3 | Base items | 0.250 | |||
| 25100630 | SQ YD | EROSION CONTROL BLANKET | Base items | 787.000 | |||
| 28000400 | FOOT | PERIMETER EROSION BARRIER | Base items | 1,580.000 | |||
| 30200750 | SQ YD | PROCESSING MODIFIED SOIL 14" | Base items | 28,307.000 | |||
| 30201700 | TON | PORTLAND CEMENT | Base items | 1,710.000 | |||
| 40200800 | TON | AGGREGATE SURFACE COURSE, TYPE B | Base items | 17.000 | |||
| 48102100 | TON | AGGREGATE WEDGE SHOULDER, TYPE B | Base items | 780.000 | |||
| 50105220 | FOOT | PIPE CULVERT REMOVAL | Base items | 68.000 | |||
| 54010603 | FOOT | PRECAST CONCRETE BOX CULVERTS 6' X 3' | Base items | 40.000 | |||
| 54205053 | FOOT | PIPE CULVERTS, SPECIAL 18" | Base items | 35.000 | |||
| 59300100 | CU YD | CONTROLLED LOW-STRENGTH MATERIAL | Base items | 70.000 | |||
| 61101013 | FOOT | STORM SEWERS PROTECTED, CLASS A, 12" | Base items | 40.000 | |||
| 61133100 | EACH | FIELD TILE JUNCTION VAULTS, 2' DIA. | Base items | 4.000 | |||
| 61139900 | FOOT | STORM SEWERS (SPECIAL), 6" | Base items | 8.000 | |||
| 61140200 | FOOT | STORM SEWERS (SPECIAL), 12" | Base items | 6.000 | |||
| 67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| LR403200 | TON | BITUMINOUS MATERIALS (PRIME COAT) | Base items | 42.000 | |||
| LR403300 | SQ YD | SURFACE PROFILE MILLING | Base items | 28,307.000 | |||
| LR403400 | TON | BITUMINOUS MATERIALS (COVER AND SEAL COATS) | Base items | 125.000 | |||
| LR403500 | TON | COVER COAT AGGREGATE | Base items | 653.000 | |||
| LR403600 | TON | SEAL COAT AGGREGATE | Base items | 327.000 | |||
| X1700063 | EACH | CONCRETE HEADWALL (SPECIAL) | Base items | 2.000 | |||
| X3580300 | TON | AGGREGATE BASE REPAIR (SPECIAL) | Base items | 61.000 | |||
| X5810103 | SQ YD | MEMBRANE WATERPROOFING SYSTEM FOR BURIED STRUCTURES | Base items | 41.000 | |||
| X6050065 | EACH | REMOVING INLETS (SPECIAL) | Base items | 2.000 | |||
| X6110073 | FOOT | EXISTING FIELD TILE REMOVAL | Base items | 44.000 | |||
| XX008873 | TON | AGGREGATE SURFACE COURSE (SPECIAL) | Base items | 304.000 | |||
| XX009289 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD BLR 21 | Base items | 1.000 | |||
| No More Pay Items | |||||||