Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
3 | 4 | 0.00 | 0.00 | N/A |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
25 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200100 | CU YD | EARTH EXCAVATION | Base items | 705.000 | |||
21001000 | SQ YD | GEOTECHNICAL FABRIC FOR GROUND STABILIZATION | Base items | 485.000 | |||
21101505 | CU YD | TOPSOIL EXCAVATION AND PLACEMENT | Base items | 10.000 | |||
28000400 | FOOT | PERIMETER EROSION BARRIER | Base items | 200.000 | |||
28000510 | EACH | INLET FILTERS | Base items | 1.000 | |||
35101800 | SQ YD | AGGREGATE BASE COURSE, TYPE B 6" | Base items | 485.000 | |||
35102000 | SQ YD | AGGREGATE BASE COURSE, TYPE B 8" | Base items | 2,623.000 | |||
40600275 | POUND | BITUMINOUS MATERIALS (PRIME COAT) | Base items | 590.000 | |||
40602978 | TON | HOT-MIX ASPHALT BINDER COURSE, IL- 9.5, N50 | Base items | 367.000 | |||
40604050 | TON | HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "C", N50 | Base items | 220.000 | |||
42000401 | SQ YD | PORTLAND CEMENT CONCRETE PAVEMENT 9" (JOINTED) | Base items | 485.000 | |||
44000100 | SQ YD | PAVEMENT REMOVAL | Base items | 550.000 | |||
44200050 | SQ YD | WELDED WIRE REINFORCEMENT | Base items | 485.000 | |||
60255700 | EACH | MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, OPEN LID | Base items | 2.000 | |||
60600605 | FOOT | CONCRETE CURB, TYPE B | Base items | 550.000 | |||
60603800 | FOOT | COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 | Base items | 82.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70100450 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701201 | Base items | 1.000 | |||
X0350810 | EACH | BOLLARD REMOVAL | Base items | 26.000 | |||
Z0001110 | EACH | GAS VALVE TO BE ADJUSTED | Base items | 1.000 | |||
Z0004002 | EACH | BOLLARDS | Base items | 26.000 | |||
Z0004544 | SQ YD | HOT-MIX ASPHALT DRIVEWAY PAVEMENT REMOVAL | Base items | 3,012.000 | |||
Z0012450 | CU YD | CONCRETE STEPS | Base items | 3.000 | |||
Z0013798 | L SUM | CONSTRUCTION LAYOUT | Base items | 1.000 | |||
No More Pay Items |