Home > Notice of Letting > Contract Detail

April 24, 2026 Letting 12:00 PM
173-76U66

Bulletin Description

21.4 miles of underdrain cleaning and headwall replacement on IL 255 from I-270 to US 67 in Godfrey.
Region District DBE % VBP % Federal Project #
5 8 0.00 0.00 N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Madison
  • FAP 310
  • IL 255, US 67
  • 60-(8,9,10,11,12,13,14,15)I
  • C-98-130-25
  • 0-02180-8003
Contract Specifics
55 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (4 Submitted / 4 Answered ) Questions not accepted as of April 14, 2026 04:30 PM.

  • How will the department determine if the contractor has successfully cleaned the underdrain? Will the department be running cameras through the underdrains to determine cleanliness or the nature of obstructions or dead ends?
    The contractor should bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications available online. (04/03/2026)

  • The special provision for CLEANING PIPE UNDERDRAIN says restoration should include pavement patching. Is the intention to remove shoulder for every Tee in order to clean longitudinally with the pavement?
    The intent of the special provision is not to require removal of the shoulder at every tee to facilitate longitudinal cleaning. Cleaning of the pipe underdrains is expected to be performed through existing outlets, cleanouts, or other accessible points wherever feasible. Pavement or shoulder removal and patching would only be required where necessary to access the system and effectively complete the cleaning, as determined in the field and approved by the Engineer. (04/02/2026)

  • The special provision for CLEANING PIPE UNDERDRAIN says to report to the engineer any blockages that cannot be cleared with standard cleaning methods. If additional cleaning methods are needed will they be paid for per 109.04?
    Yes, if blockages cannot be cleared using standard cleaning methods and additional work or alternative methods are required beyond the scope of the special provision, such work would be addressed in accordance with Article 109.04 of the Standard Specifications, subject to the Engineer’s review and approval. (04/02/2026)

  • The Special Provisions call out REMOVE AND REPLACE CONCRETE HEADWALLS FOR PIPE UNDERDRAINS as a single pay item to be paid for as REMOVE AND REPLACE CONCRETE HEADWALLS FOR PIPE UNDERDRAINS, per each. There are two pay items for this work, REMOVE CONCRETE HEADWALLS FOR PIPE DRAINS and CONCRETE HEADWALL (SPECIAL). Can you clarify your intent?
    The contractor should bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications available online. (04/02/2026)

Authorized Bidders

  • 1487 DMS Contracting, Inc.
    10243 Fuesser Road
    Mascoutah, IL 62258
    PO Box 122
    Mascoutah, IL 62258
    Phone: (618) 566-9114 Fax: (618) 566-3145 Email: estimating@dmscontracting.com

  • 0338 Baxmeyer Construction, Inc.
    1034 Floraville Road
    Waterloo, IL 62298
    Phone: (618) 939-3000 Fax: (618) 939-4299 Email: estimator@baxmeyerconstruction.com

  • 2308 Hank's Excavating & Landscaping, Inc.
    5825 West State Route 161
    Belleville, IL 62223
    Phone: (618) 398-5556 Fax: (618) 398-2729 Email: No Record

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
67100100 L SUM MOBILIZATION Base items 1.000
70100420 EACH TRAFFIC CONTROL AND PROTECTION, STANDARD 701411 Base items 38.000
70100700 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701406 Base items 1.000
70100800 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701401 Base items 1.000
70100825 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701456 Base items 1.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 364.000
X6010800 FOOT CLEANING PIPE UNDERDRAIN Base items 378,704.000
X6015015 EACH REMOVE AND REPLACE CONCRETE HEADWALLS FOR PIPE UNDERDRAINS Base items 685.000
Z0076604 HOUR TRAINEES TRAINING PROGRAM GRADUATE Base items 500.000 $15.00
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.