                                               ILLINOIS DEPARTMENT OF TRANSPORTATION                                      PAGE:    1
 03/13/19  13:12:50                   U N I T  P R I C E   T A B U L A T I O N   O F   B I D S
 LETTING DATE: 01/18/2019  LETTING TYPE: SCHEDULED                                 CONTRACT NUMBER: 76J12  LETTING ITEM NUMBER: 126
 RESPONSIBLE DISTRICT: 08                                                                                  BIDS LOCKED: Y
 SECTION: 66-BR                                    COUNTY: MADISON                                         ESTIMATE:
                                                      --------------------------
                                                      SUMMARY OF CONTRACTOR BIDS
                                                      --------------------------

                                                             "AS READ"          SUMMATION    SUMMATION OF                       NBR
 BIDR                     CONTR        COMB  ITEM  CONTR      BIDDER            OF BIDDER     CALCULATED   LOW   BIDR CALC      BLANK
 NBR   BIDDER NAME        GROUP  COMB  GRP   NBR   GROUP      TOTAL PRICE       EXTENSIONS    EXTENSIONS   BID   EXTENSION DIFF BIDS


 0338  Baxmeyer Construction, Inc.
                          NO ALT                              644,577.77 *     644,577.77     644,577.77    *

 3085  Keeley & Sons, Inc.
                          NO ALT                              662,488.96       662,488.96     662,488.96

 3108  Keller Construction, Inc.
                          NO ALT                              647,513.91       647,513.91     647,513.91

 3157  The Kilian Corporation
                          NO ALT                              689,984.27       689,984.27     689,984.27

 4757  Plocher Construction Company, Inc.
                          NO ALT                              720,915.00       720,915.00     720,915.00

 4928  RCS Construction, Inc.
                          NO ALT                              658,947.51       658,947.51     658,947.51

 5802  Stutz Excavating, Inc.
                          NO ALT                              669,557.10       669,557.10     669,557.10

 **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT =      87
                                                       ----------------------
                                                       DETAIL CONTRACTOR BIDS
                                                       ----------------------

    ITEM NBR  ITEM DESCRIPTION                                    UNIT OF     UNIT        BIDDER         CALCULATED  BIDR CALC
 BIDR NBR  BIDDER NAME                                  QUANTITY  MEASURE     PRICE       EXTENSION      EXTENSION   EXTENSION DIFF


    A2007616  T-TAXODIUM DIS      2                        4.000     EACH
 0338      Baxmeyer Construction, Inc.                                    450.0000        1,800.00        1,800.00
 3085      Keeley & Sons, Inc.                                            326.4000        1,305.60        1,305.60
 3108      Keller Construction, Inc.                                      365.0000        1,460.00        1,460.00
 4757      Plocher Construction Company, Inc.                             395.0000        1,580.00        1,580.00
 4928      RCS Construction, Inc.                                         350.0000        1,400.00        1,400.00
 5802      Stutz Excavating, Inc.                                         445.0000        1,780.00        1,780.00
 3157      The Kilian Corporation                                         325.0000        1,300.00        1,300.00

    B2000416  T-ACER GRIS TF      2                        4.000     EACH
 0338      Baxmeyer Construction, Inc.                                    450.0000        1,800.00        1,800.00
 3085      Keeley & Sons, Inc.                                            326.4000        1,305.60        1,305.60
 3108      Keller Construction, Inc.                                      365.0000        1,460.00        1,460.00
 4757      Plocher Construction Company, Inc.                             395.0000        1,580.00        1,580.00
 4928      RCS Construction, Inc.                                         350.0000        1,400.00        1,400.00
 5802      Stutz Excavating, Inc.                                         445.0000        1,780.00        1,780.00
 3157      The Kilian Corporation                                         325.0000        1,300.00        1,300.00

    B2001616  T-CRAT CRU-I TF     2                        4.000     EACH
 0338      Baxmeyer Construction, Inc.                                    450.0000        1,800.00        1,800.00
 3085      Keeley & Sons, Inc.                                            326.4000        1,305.60        1,305.60
 3108      Keller Construction, Inc.                                      365.0000        1,460.00        1,460.00
 4757      Plocher Construction Company, Inc.                             395.0000        1,580.00        1,580.00
 4928      RCS Construction, Inc.                                         350.0000        1,400.00        1,400.00
 5802      Stutz Excavating, Inc.                                         445.0000        1,780.00        1,780.00
 3157      The Kilian Corporation                                         325.0000        1,300.00        1,300.00

    D2001524  E-JUNIP VIRG       2'                        4.000     EACH
 0338      Baxmeyer Construction, Inc.                                    400.0000        1,600.00        1,600.00
 3085      Keeley & Sons, Inc.                                             96.9000          387.60          387.60
 3108      Keller Construction, Inc.                                      235.0000          940.00          940.00
 4757      Plocher Construction Company, Inc.                             250.0000        1,000.00        1,000.00
 4928      RCS Construction, Inc.                                         100.0000          400.00          400.00
 5802      Stutz Excavating, Inc.                                         395.0000        1,580.00        1,580.00
 3157      The Kilian Corporation                                          97.0000          388.00          388.00

    X0323265  REMOVE EXIST RIPRAP                        109.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     16.0000        1,744.00        1,744.00
 3085      Keeley & Sons, Inc.                                             16.9000        1,842.10        1,842.10
 3108      Keller Construction, Inc.                                       10.8400        1,181.56        1,181.56
 4757      Plocher Construction Company, Inc.                              11.0000        1,199.00        1,199.00
 4928      RCS Construction, Inc.                                          12.0000        1,308.00        1,308.00
 5802      Stutz Excavating, Inc.                                          16.0000        1,744.00        1,744.00
 3157      The Kilian Corporation                                          10.0000        1,090.00        1,090.00

    X0900064  MEMBR WTRPR SYS B STR                      132.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     57.0000        7,524.00        7,524.00
 3085      Keeley & Sons, Inc.                                             64.8300        8,557.56        8,557.56
 3108      Keller Construction, Inc.                                       42.3500        5,590.20        5,590.20
 4757      Plocher Construction Company, Inc.                              42.5000        5,610.00        5,610.00
 4928      RCS Construction, Inc.                                          17.5000        2,310.00        2,310.00
 5802      Stutz Excavating, Inc.                                          50.0000        6,600.00        6,600.00
 3157      The Kilian Corporation                                          40.0000        5,280.00        5,280.00

    X6660445  ROW/PROPERTY CORNERS                        11.000     EACH
 0338      Baxmeyer Construction, Inc.                                    320.0000        3,520.00        3,520.00
 3085      Keeley & Sons, Inc.                                            265.0000        2,915.00        2,915.00
 3108      Keller Construction, Inc.                                      250.0000        2,750.00        2,750.00
 4757      Plocher Construction Company, Inc.                             100.0000        1,100.00        1,100.00
 4928      RCS Construction, Inc.                                         195.0000        2,145.00        2,145.00
 5802      Stutz Excavating, Inc.                                         265.0000        2,915.00        2,915.00
 3157      The Kilian Corporation                                         170.0000        1,870.00        1,870.00

    X7030005  TEMP PAVT MKING REMOV                      623.000    SQ FT
 0338      Baxmeyer Construction, Inc.                                      0.0100            6.23            6.23
 3085      Keeley & Sons, Inc.                                              1.0000          623.00          623.00
 3108      Keller Construction, Inc.                                        0.0100            6.23            6.23
 4757      Plocher Construction Company, Inc.                               2.8000        1,744.40        1,744.40
 4928      RCS Construction, Inc.                                           1.0000          623.00          623.00
 5802      Stutz Excavating, Inc.                                           0.0100            6.23            6.23
 3157      The Kilian Corporation                                           0.0100            6.23            6.23

    Z0013798  CONSTRUCTION LAYOUT                          1.000    L SUM
 0338      Baxmeyer Construction, Inc.                                  7,000.0000        7,000.00        7,000.00
 3085      Keeley & Sons, Inc.                                          8,670.0000        8,670.00        8,670.00
 3108      Keller Construction, Inc.                                    6,100.0000        6,100.00        6,100.00
 4757      Plocher Construction Company, Inc.                           8,500.0000        8,500.00        8,500.00
 4928      RCS Construction, Inc.                                      10,000.0000       10,000.00       10,000.00
 5802      Stutz Excavating, Inc.                                      12,000.0000       12,000.00       12,000.00
 3157      The Kilian Corporation                                       8,500.0000        8,500.00        8,500.00

    Z0016702  DETOUR SIGNING                               1.000    L SUM
 0338      Baxmeyer Construction, Inc.                                  5,250.0000        5,250.00        5,250.00
 3085      Keeley & Sons, Inc.                                          5,049.0000        5,049.00        5,049.00
 3108      Keller Construction, Inc.                                    4,950.0000        4,950.00        4,950.00
 4757      Plocher Construction Company, Inc.                           6,000.0000        6,000.00        6,000.00
 4928      RCS Construction, Inc.                                       5,500.0000        5,500.00        5,500.00
 5802      Stutz Excavating, Inc.                                       5,200.0000        5,200.00        5,200.00
 3157      The Kilian Corporation                                       5,100.0000        5,100.00        5,100.00

    Z0033700  LONG JOINT SEALANT                         618.000     FOOT
 0338      Baxmeyer Construction, Inc.                                     18.5000       11,433.00       11,433.00
 3085      Keeley & Sons, Inc.                                             17.8300       11,018.94       11,018.94
 3108      Keller Construction, Inc.                                       17.4800       10,802.64       10,802.64
 4757      Plocher Construction Company, Inc.                              17.4800       10,802.64       10,802.64
 4928      RCS Construction, Inc.                                          19.2500       11,896.50       11,896.50
 5802      Stutz Excavating, Inc.                                          14.5000        8,961.00        8,961.00
 3157      The Kilian Corporation                                          11.7500        7,261.50        7,261.50

    Z0076600  TRAINEES                                 1,000.000     HOUR
 0338      Baxmeyer Construction, Inc.                                      0.8000          800.00          800.00
 3085      Keeley & Sons, Inc.                                              0.8000          800.00          800.00
 3108      Keller Construction, Inc.                                        0.8000          800.00          800.00
 4757      Plocher Construction Company, Inc.                               0.8000          800.00          800.00
 4928      RCS Construction, Inc.                                           0.8000          800.00          800.00
 5802      Stutz Excavating, Inc.                                           0.8000          800.00          800.00
 3157      The Kilian Corporation                                           0.8000          800.00          800.00

    Z0076604  TRAINEES TPG                             1,000.000     HOUR
 0338      Baxmeyer Construction, Inc.                                     15.0000       15,000.00       15,000.00
 3085      Keeley & Sons, Inc.                                             15.0000       15,000.00       15,000.00
 3108      Keller Construction, Inc.                                       15.0000       15,000.00       15,000.00
 4757      Plocher Construction Company, Inc.                              15.0000       15,000.00       15,000.00
 4928      RCS Construction, Inc.                                          15.0000       15,000.00       15,000.00
 5802      Stutz Excavating, Inc.                                          15.0000       15,000.00       15,000.00
 3157      The Kilian Corporation                                          15.0000       15,000.00       15,000.00

    20100110  TREE REMOV 6-15                             86.000     UNIT
 0338      Baxmeyer Construction, Inc.                                     24.0000        2,064.00        2,064.00
 3085      Keeley & Sons, Inc.                                             24.9000        2,141.40        2,141.40
 3108      Keller Construction, Inc.                                       22.7500        1,956.50        1,956.50
 4757      Plocher Construction Company, Inc.                              22.7500        1,956.50        1,956.50
 4928      RCS Construction, Inc.                                          25.0000        2,150.00        2,150.00
 5802      Stutz Excavating, Inc.                                          21.5000        1,849.00        1,849.00
 3157      The Kilian Corporation                                          29.0000        2,494.00        2,494.00

    20100210  TREE REMOV OVER 15                         137.000     UNIT
 0338      Baxmeyer Construction, Inc.                                     36.0000        4,932.00        4,932.00
 3085      Keeley & Sons, Inc.                                             31.6000        4,329.20        4,329.20
 3108      Keller Construction, Inc.                                       34.2500        4,692.25        4,692.25
 4757      Plocher Construction Company, Inc.                              34.2500        4,692.25        4,692.25
 4928      RCS Construction, Inc.                                          37.7500        5,171.75        5,171.75
 5802      Stutz Excavating, Inc.                                          38.5000        5,274.50        5,274.50
 3157      The Kilian Corporation                                          36.0000        4,932.00        4,932.00

    20200100  EARTH EXCAVATION                           620.000    CU YD
 0338      Baxmeyer Construction, Inc.                                     25.0000       15,500.00       15,500.00
 3085      Keeley & Sons, Inc.                                             18.9000       11,718.00       11,718.00
 3108      Keller Construction, Inc.                                       18.7000       11,594.00       11,594.00
 4757      Plocher Construction Company, Inc.                              18.0000       11,160.00       11,160.00
 4928      RCS Construction, Inc.                                          26.2500       16,275.00       16,275.00
 5802      Stutz Excavating, Inc.                                          24.7000       15,314.00       15,314.00
 3157      The Kilian Corporation                                          25.0000       15,500.00       15,500.00

    20300100  CHANNEL EXCAVATION                         440.000    CU YD
 0338      Baxmeyer Construction, Inc.                                     26.0000       11,440.00       11,440.00
 3085      Keeley & Sons, Inc.                                             16.8500        7,414.00        7,414.00
 3108      Keller Construction, Inc.                                       16.3500        7,194.00        7,194.00
 4757      Plocher Construction Company, Inc.                              18.0000        7,920.00        7,920.00
 4928      RCS Construction, Inc.                                          20.0000        8,800.00        8,800.00
 5802      Stutz Excavating, Inc.                                          16.6500        7,326.00        7,326.00
 3157      The Kilian Corporation                                          20.0000        8,800.00        8,800.00

    20400800  FURNISHED EXCAVATION                        95.000    CU YD
 0338      Baxmeyer Construction, Inc.                                      0.0100            0.95            0.95
 3085      Keeley & Sons, Inc.                                             26.9000        2,555.50        2,555.50
 3108      Keller Construction, Inc.                                        0.0100            0.95            0.95
 4757      Plocher Construction Company, Inc.                              18.0000        1,710.00        1,710.00
 4928      RCS Construction, Inc.                                           0.0100            0.95            0.95
 5802      Stutz Excavating, Inc.                                          12.9000        1,225.50        1,225.50
 3157      The Kilian Corporation                                           0.0100            0.95            0.95

    20800150  TRENCH BACKFILL                            150.000    CU YD
 0338      Baxmeyer Construction, Inc.                                     29.0000        4,350.00        4,350.00
 3085      Keeley & Sons, Inc.                                             37.8000        5,670.00        5,670.00
 3108      Keller Construction, Inc.                                        0.0100            1.50            1.50
 4757      Plocher Construction Company, Inc.                              51.0000        7,650.00        7,650.00
 4928      RCS Construction, Inc.                                          43.0000        6,450.00        6,450.00
 5802      Stutz Excavating, Inc.                                          22.7500        3,412.50        3,412.50
 3157      The Kilian Corporation                                           0.0100            1.50            1.50

    25000210  SEEDING CL  2A                                .750     ACRE
 0338      Baxmeyer Construction, Inc.                                  3,050.0000        2,287.50        2,287.50
 3085      Keeley & Sons, Inc.                                          2,550.0000        1,912.50        1,912.50
 3108      Keller Construction, Inc.                                    1,725.0000        1,293.75        1,293.75
 4757      Plocher Construction Company, Inc.                           1,787.0000        1,340.25        1,340.25
 4928      RCS Construction, Inc.                                       2,750.0000        2,062.50        2,062.50
 5802      Stutz Excavating, Inc.                                       3,020.0000        2,265.00        2,265.00
 3157      The Kilian Corporation                                       2,600.0000        1,950.00        1,950.00

    25000400  NITROGEN FERT NUTR                          49.000    POUND
 0338      Baxmeyer Construction, Inc.                                      1.2500           61.25           61.25
 3085      Keeley & Sons, Inc.                                              1.4300           70.07           70.07
 3108      Keller Construction, Inc.                                        1.1500           56.35           56.35
 4757      Plocher Construction Company, Inc.                               1.2300           60.27           60.27
 4928      RCS Construction, Inc.                                           1.5000           73.50           73.50
 5802      Stutz Excavating, Inc.                                           1.2000           58.80           58.80
 3157      The Kilian Corporation                                           1.4500           71.05           71.05

    25000500  PHOSPHORUS FERT NUTR                        49.000    POUND
 0338      Baxmeyer Construction, Inc.                                      1.2500           61.25           61.25
 3085      Keeley & Sons, Inc.                                              1.4300           70.07           70.07
 3108      Keller Construction, Inc.                                        1.1500           56.35           56.35
 4757      Plocher Construction Company, Inc.                               1.2300           60.27           60.27
 4928      RCS Construction, Inc.                                           1.5000           73.50           73.50
 5802      Stutz Excavating, Inc.                                           1.2000           58.80           58.80
 3157      The Kilian Corporation                                           1.4500           71.05           71.05

    25000600  POTASSIUM FERT NUTR                         49.000    POUND
 0338      Baxmeyer Construction, Inc.                                      1.2500           61.25           61.25
 3085      Keeley & Sons, Inc.                                              1.4300           70.07           70.07
 3108      Keller Construction, Inc.                                        1.1500           56.35           56.35
 4757      Plocher Construction Company, Inc.                               1.2300           60.27           60.27
 4928      RCS Construction, Inc.                                           1.5000           73.50           73.50
 5802      Stutz Excavating, Inc.                                           1.2000           58.80           58.80
 3157      The Kilian Corporation                                           1.4500           71.05           71.05

    25100115  MULCH METHOD 2                                .750     ACRE
 0338      Baxmeyer Construction, Inc.                                  1,500.0000        1,125.00        1,125.00
 3085      Keeley & Sons, Inc.                                          2,550.0000        1,912.50        1,912.50
 3108      Keller Construction, Inc.                                    2,000.0000        1,500.00        1,500.00
 4757      Plocher Construction Company, Inc.                           2,449.0000        1,836.75        1,836.75
 4928      RCS Construction, Inc.                                       2,750.0000        2,062.50        2,062.50
 5802      Stutz Excavating, Inc.                                       1,500.0000        1,125.00        1,125.00
 3157      The Kilian Corporation                                       2,550.0000        1,912.50        1,912.50

    25100630  EROSION CONTR BLANKET                    1,179.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                      1.5000        1,768.50        1,768.50
 3085      Keeley & Sons, Inc.                                              1.3800        1,627.02        1,627.02
 3108      Keller Construction, Inc.                                        1.3500        1,591.65        1,591.65
 4757      Plocher Construction Company, Inc.                               1.6900        1,992.51        1,992.51
 4928      RCS Construction, Inc.                                           1.5000        1,768.50        1,768.50
 5802      Stutz Excavating, Inc.                                           1.4000        1,650.60        1,650.60
 3157      The Kilian Corporation                                           1.4000        1,650.60        1,650.60

    28000250  TEMP EROS CONTR SEED                       537.000    POUND
 0338      Baxmeyer Construction, Inc.                                      1.0000          537.00          537.00
 3085      Keeley & Sons, Inc.                                              5.1000        2,738.70        2,738.70
 3108      Keller Construction, Inc.                                        1.7500          939.75          939.75
 4757      Plocher Construction Company, Inc.                               1.9600        1,052.52        1,052.52
 4928      RCS Construction, Inc.                                           0.0100            5.37            5.37
 5802      Stutz Excavating, Inc.                                           2.0000        1,074.00        1,074.00
 3157      The Kilian Corporation                                           3.0000        1,611.00        1,611.00

    28000400  PERIMETER EROS BAR                         250.000     FOOT
 0338      Baxmeyer Construction, Inc.                                      5.5000        1,375.00        1,375.00
 3085      Keeley & Sons, Inc.                                              7.3500        1,837.50        1,837.50
 3108      Keller Construction, Inc.                                        2.5100          627.50          627.50
 4757      Plocher Construction Company, Inc.                               2.5100          627.50          627.50
 4928      RCS Construction, Inc.                                           2.7500          687.50          687.50
 5802      Stutz Excavating, Inc.                                           4.0000        1,000.00        1,000.00
 3157      The Kilian Corporation                                           7.5000        1,875.00        1,875.00

    28000500  INLET & PIPE PROTECT                         4.000     EACH
 0338      Baxmeyer Construction, Inc.                                     65.0000          260.00          260.00
 3085      Keeley & Sons, Inc.                                            267.4500        1,069.80        1,069.80
 3108      Keller Construction, Inc.                                       77.6900          310.76          310.76
 4757      Plocher Construction Company, Inc.                             110.0000          440.00          440.00
 4928      RCS Construction, Inc.                                         125.0000          500.00          500.00
 5802      Stutz Excavating, Inc.                                          45.0000          180.00          180.00
 3157      The Kilian Corporation                                         115.0000          460.00          460.00

    28001100  TEMP EROS CONTR BLANK                    1,599.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                      1.7500        2,798.25        2,798.25
 3085      Keeley & Sons, Inc.                                              2.2500        3,597.75        3,597.75
 3108      Keller Construction, Inc.                                        1.6600        2,654.34        2,654.34
 4757      Plocher Construction Company, Inc.                               1.6600        2,654.34        2,654.34
 4928      RCS Construction, Inc.                                           0.0100           15.99           15.99
 5802      Stutz Excavating, Inc.                                           2.0000        3,198.00        3,198.00
 3157      The Kilian Corporation                                           2.3000        3,677.70        3,677.70

    28100105  STONE RIPRAP CL A3                         127.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     18.5000        2,349.50        2,349.50
 3085      Keeley & Sons, Inc.                                             43.9000        5,575.30        5,575.30
 3108      Keller Construction, Inc.                                       18.7700        2,383.79        2,383.79
 4757      Plocher Construction Company, Inc.                              21.0000        2,667.00        2,667.00
 4928      RCS Construction, Inc.                                          16.5000        2,095.50        2,095.50
 5802      Stutz Excavating, Inc.                                          18.0000        2,286.00        2,286.00
 3157      The Kilian Corporation                                          24.0000        3,048.00        3,048.00

    28100107  STONE RIPRAP CL A4                         302.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     37.2500       11,249.50       11,249.50
 3085      Keeley & Sons, Inc.                                             49.8000       15,039.60       15,039.60
 3108      Keller Construction, Inc.                                       28.1300        8,495.26        8,495.26
 4757      Plocher Construction Company, Inc.                              40.0000       12,080.00       12,080.00
 4928      RCS Construction, Inc.                                          36.7500       11,098.50       11,098.50
 5802      Stutz Excavating, Inc.                                          41.0000       12,382.00       12,382.00
 3157      The Kilian Corporation                                          40.0000       12,080.00       12,080.00

    28200200  FILTER FABRIC                              302.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                      4.0000        1,208.00        1,208.00
 3085      Keeley & Sons, Inc.                                              4.4500        1,343.90        1,343.90
 3108      Keller Construction, Inc.                                        2.5000          755.00          755.00
 4757      Plocher Construction Company, Inc.                               2.0000          604.00          604.00
 4928      RCS Construction, Inc.                                           2.0000          604.00          604.00
 5802      Stutz Excavating, Inc.                                           2.0000          604.00          604.00
 3157      The Kilian Corporation                                           1.2500          377.50          377.50

    31100100  SUB GRAN MAT A                             237.000      TON
 0338      Baxmeyer Construction, Inc.                                     20.5000        4,858.50        4,858.50
 3085      Keeley & Sons, Inc.                                             17.1500        4,064.55        4,064.55
 3108      Keller Construction, Inc.                                       21.9400        5,199.78        5,199.78
 4757      Plocher Construction Company, Inc.                              25.0000        5,925.00        5,925.00
 4928      RCS Construction, Inc.                                          25.0000        5,925.00        5,925.00
 5802      Stutz Excavating, Inc.                                          21.0000        4,977.00        4,977.00
 3157      The Kilian Corporation                                          24.0000        5,688.00        5,688.00

    31101900  SUB GRAN MAT C                              30.000      TON
 0338      Baxmeyer Construction, Inc.                                    122.7500        3,682.50        3,682.50
 3085      Keeley & Sons, Inc.                                            118.2300        3,546.90        3,546.90
 3108      Keller Construction, Inc.                                      115.9100        3,477.30        3,477.30
 4757      Plocher Construction Company, Inc.                             116.0000        3,480.00        3,480.00
 4928      RCS Construction, Inc.                                         127.5000        3,825.00        3,825.00
 5802      Stutz Excavating, Inc.                                          76.4500        2,293.50        2,293.50
 3157      The Kilian Corporation                                          30.0000          900.00          900.00

    40200100  AGG SURF CSE A                               7.000      TON
 0338      Baxmeyer Construction, Inc.                                     45.0000          315.00          315.00
 3085      Keeley & Sons, Inc.                                             27.8000          194.60          194.60
 3108      Keller Construction, Inc.                                       41.9000          293.30          293.30
 4757      Plocher Construction Company, Inc.                              70.0000          490.00          490.00
 4928      RCS Construction, Inc.                                          38.0000          266.00          266.00
 5802      Stutz Excavating, Inc.                                          35.0000          245.00          245.00
 3157      The Kilian Corporation                                          35.0000          245.00          245.00

    40201000  AGGREGATE-TEMP ACCESS                       24.000      TON
 0338      Baxmeyer Construction, Inc.                                     30.0000          720.00          720.00
 3085      Keeley & Sons, Inc.                                             26.4500          634.80          634.80
 3108      Keller Construction, Inc.                                       24.7500          594.00          594.00
 4757      Plocher Construction Company, Inc.                              30.0000          720.00          720.00
 4928      RCS Construction, Inc.                                          26.5000          636.00          636.00
 5802      Stutz Excavating, Inc.                                          30.0000          720.00          720.00
 3157      The Kilian Corporation                                          28.0000          672.00          672.00

    40600290  BIT MATLS TACK CT                        1,011.000    POUND
 0338      Baxmeyer Construction, Inc.                                      2.0000        2,022.00        2,022.00
 3085      Keeley & Sons, Inc.                                              2.0400        2,062.44        2,062.44
 3108      Keller Construction, Inc.                                        2.0000        2,022.00        2,022.00
 4757      Plocher Construction Company, Inc.                               2.0000        2,022.00        2,022.00
 4928      RCS Construction, Inc.                                           2.2500        2,274.75        2,274.75
 5802      Stutz Excavating, Inc.                                           1.1000        1,112.10        1,112.10
 3157      The Kilian Corporation                                           1.0000        1,011.00        1,011.00

    40600990  TEMPORARY RAMP                              45.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                      7.0000          315.00          315.00
 3085      Keeley & Sons, Inc.                                              6.8600          308.70          308.70
 3108      Keller Construction, Inc.                                        6.7200          302.40          302.40
 4757      Plocher Construction Company, Inc.                               6.7200          302.40          302.40
 4928      RCS Construction, Inc.                                           7.5000          337.50          337.50
 5802      Stutz Excavating, Inc.                                           0.0100            0.45            0.45
 3157      The Kilian Corporation                                           0.0100            0.45            0.45

    40603085  HMA BC IL-19.0  N70                        358.000      TON
 0338      Baxmeyer Construction, Inc.                                    105.5000       37,769.00       37,769.00
 3085      Keeley & Sons, Inc.                                            101.7500       36,426.50       36,426.50
 3108      Keller Construction, Inc.                                       99.7500       35,710.50       35,710.50
 4757      Plocher Construction Company, Inc.                              99.7500       35,710.50       35,710.50
 4928      RCS Construction, Inc.                                         110.0000       39,380.00       39,380.00
 5802      Stutz Excavating, Inc.                                          93.0000       33,294.00       33,294.00
 3157      The Kilian Corporation                                         110.0000       39,380.00       39,380.00

    40603315  HMA SC "C"   N70                           111.000      TON
 0338      Baxmeyer Construction, Inc.                                    167.0000       18,537.00       18,537.00
 3085      Keeley & Sons, Inc.                                            161.1300       17,885.43       17,885.43
 3108      Keller Construction, Inc.                                      157.9700       17,534.67       17,534.67
 4757      Plocher Construction Company, Inc.                             157.9700       17,534.67       17,534.67
 4928      RCS Construction, Inc.                                         175.0000       19,425.00       19,425.00
 5802      Stutz Excavating, Inc.                                         119.0000       13,209.00       13,209.00
 3157      The Kilian Corporation                                         125.0000       13,875.00       13,875.00

    40700100  BIT MATLS TACK CT                           94.000    POUND
 0338      Baxmeyer Construction, Inc.                                      4.2500          399.50          399.50
 3085      Keeley & Sons, Inc.                                              4.0800          383.52          383.52
 3108      Keller Construction, Inc.                                        4.0000          376.00          376.00
 4757      Plocher Construction Company, Inc.                               4.0000          376.00          376.00
 4928      RCS Construction, Inc.                                           4.5000          423.00          423.00
 5802      Stutz Excavating, Inc.                                           1.5000          141.00          141.00
 3157      The Kilian Corporation                                           1.0000           94.00           94.00

    40701901  HMA PAVT FD   11                           208.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                    101.5000       21,112.00       21,112.00
 3085      Keeley & Sons, Inc.                                             97.8200       20,346.56       20,346.56
 3108      Keller Construction, Inc.                                       95.9000       19,947.20       19,947.20
 4757      Plocher Construction Company, Inc.                              95.9000       19,947.20       19,947.20
 4928      RCS Construction, Inc.                                         105.0000       21,840.00       21,840.00
 5802      Stutz Excavating, Inc.                                          63.7000       13,249.60       13,249.60
 3157      The Kilian Corporation                                          75.0000       15,600.00       15,600.00

    40800050  INCIDENTAL HMA SURF                          7.000      TON
 0338      Baxmeyer Construction, Inc.                                    322.0000        2,254.00        2,254.00
 3085      Keeley & Sons, Inc.                                            310.0100        2,170.07        2,170.07
 3108      Keller Construction, Inc.                                      303.9300        2,127.51        2,127.51
 4757      Plocher Construction Company, Inc.                             303.9300        2,127.51        2,127.51
 4928      RCS Construction, Inc.                                         335.0000        2,345.00        2,345.00
 5802      Stutz Excavating, Inc.                                         225.0000        1,575.00        1,575.00
 3157      The Kilian Corporation                                         255.0000        1,785.00        1,785.00

    44000100  PAVEMENT REM                               208.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     13.0000        2,704.00        2,704.00
 3085      Keeley & Sons, Inc.                                             13.3000        2,766.40        2,766.40
 3108      Keller Construction, Inc.                                       22.6400        4,709.12        4,709.12
 4757      Plocher Construction Company, Inc.                              22.6400        4,709.12        4,709.12
 4928      RCS Construction, Inc.                                          25.0000        5,200.00        5,200.00
 5802      Stutz Excavating, Inc.                                          14.8500        3,088.80        3,088.80
 3157      The Kilian Corporation                                          20.0000        4,160.00        4,160.00

    44000155  HMA SURF REM    1 1/2                    1,232.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                      8.2500       10,164.00       10,164.00
 3085      Keeley & Sons, Inc.                                              8.0100        9,868.32        9,868.32
 3108      Keller Construction, Inc.                                        7.8500        9,671.20        9,671.20
 4757      Plocher Construction Company, Inc.                               7.8500        9,671.20        9,671.20
 4928      RCS Construction, Inc.                                           8.5000       10,472.00       10,472.00
 5802      Stutz Excavating, Inc.                                           9.3000       11,457.60       11,457.60
 3157      The Kilian Corporation                                           6.2500        7,700.00        7,700.00

    44004250  PAVED SHLD REMOVAL                         240.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     16.5000        3,960.00        3,960.00
 3085      Keeley & Sons, Inc.                                             12.9000        3,096.00        3,096.00
 3108      Keller Construction, Inc.                                        8.7200        2,092.80        2,092.80
 4757      Plocher Construction Company, Inc.                               8.7200        2,092.80        2,092.80
 4928      RCS Construction, Inc.                                           9.5000        2,280.00        2,280.00
 5802      Stutz Excavating, Inc.                                          17.2000        4,128.00        4,128.00
 3157      The Kilian Corporation                                          10.0000        2,400.00        2,400.00

    48101200  AGGREGATE SHLDS B                          112.000      TON
 0338      Baxmeyer Construction, Inc.                                     41.7500        4,676.00        4,676.00
 3085      Keeley & Sons, Inc.                                             40.3200        4,515.84        4,515.84
 3108      Keller Construction, Inc.                                       39.5200        4,426.24        4,426.24
 4757      Plocher Construction Company, Inc.                              39.5200        4,426.24        4,426.24
 4928      RCS Construction, Inc.                                          43.5000        4,872.00        4,872.00
 5802      Stutz Excavating, Inc.                                          36.7500        4,116.00        4,116.00
 3157      The Kilian Corporation                                          28.0000        3,136.00        3,136.00

    48203029  HMA SHOULDERS   8                          240.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     83.0000       19,920.00       19,920.00
 3085      Keeley & Sons, Inc.                                             79.8400       19,161.60       19,161.60
 3108      Keller Construction, Inc.                                       78.2700       18,784.80       18,784.80
 4757      Plocher Construction Company, Inc.                              78.2700       18,784.80       18,784.80
 4928      RCS Construction, Inc.                                          86.0000       20,640.00       20,640.00
 5802      Stutz Excavating, Inc.                                          50.7500       12,180.00       12,180.00
 3157      The Kilian Corporation                                          53.5000       12,840.00       12,840.00

    50100100  REM EXIST STRUCT                             1.000     EACH
 0338      Baxmeyer Construction, Inc.                                 17,800.0000       17,800.00       17,800.00
 3085      Keeley & Sons, Inc.                                         21,800.0000       21,800.00       21,800.00
 3108      Keller Construction, Inc.                                   28,000.0000       28,000.00       28,000.00
 4757      Plocher Construction Company, Inc.                          30,000.0000       30,000.00       30,000.00
 4928      RCS Construction, Inc.                                      23,500.0000       23,500.00       23,500.00
 5802      Stutz Excavating, Inc.                                      12,650.0000       12,650.00       12,650.00
 3157      The Kilian Corporation                                      23,000.0000       23,000.00       23,000.00

    50105220  PIPE CULVERT REMOV                         160.000     FOOT
 0338      Baxmeyer Construction, Inc.                                      7.0000        1,120.00        1,120.00
 3085      Keeley & Sons, Inc.                                              8.8500        1,416.00        1,416.00
 3108      Keller Construction, Inc.                                        4.4400          710.40          710.40
 4757      Plocher Construction Company, Inc.                               4.4100          705.60          705.60
 4928      RCS Construction, Inc.                                           4.8500          776.00          776.00
 5802      Stutz Excavating, Inc.                                          11.5000        1,840.00        1,840.00
 3157      The Kilian Corporation                                           8.0000        1,280.00        1,280.00

    50200100  STRUCTURE EXCAVATION                        32.000    CU YD
 0338      Baxmeyer Construction, Inc.                                     47.5000        1,520.00        1,520.00
 3085      Keeley & Sons, Inc.                                             26.4500          846.40          846.40
 3108      Keller Construction, Inc.                                       58.7300        1,879.36        1,879.36
 4757      Plocher Construction Company, Inc.                              30.0000          960.00          960.00
 4928      RCS Construction, Inc.                                          57.7500        1,848.00        1,848.00
 5802      Stutz Excavating, Inc.                                          25.8000          825.60          825.60
 3157      The Kilian Corporation                                          42.0000        1,344.00        1,344.00

    50300225  CONC STRUCT                                 13.100    CU YD
 0338      Baxmeyer Construction, Inc.                                  1,237.0000       16,204.70       16,204.70
 3085      Keeley & Sons, Inc.                                          1,390.6500       18,217.52       18,217.52
 3108      Keller Construction, Inc.                                    1,650.0000       21,615.00       21,615.00
 4757      Plocher Construction Company, Inc.                           1,100.0000       14,410.00       14,410.00
 4928      RCS Construction, Inc.                                       1,450.0000       18,995.00       18,995.00
 5802      Stutz Excavating, Inc.                                         975.0000       12,772.50       12,772.50
 3157      The Kilian Corporation                                       1,825.0000       23,907.50       23,907.50

    50500505  STUD SHEAR CONNECTORS                      128.000     EACH
 0338      Baxmeyer Construction, Inc.                                     15.5000        1,984.00        1,984.00
 3085      Keeley & Sons, Inc.                                             16.8000        2,150.40        2,150.40
 3108      Keller Construction, Inc.                                       16.0000        2,048.00        2,048.00
 4757      Plocher Construction Company, Inc.                              12.5000        1,600.00        1,600.00
 4928      RCS Construction, Inc.                                           2.1500          275.20          275.20
 5802      Stutz Excavating, Inc.                                          16.4000        2,099.20        2,099.20
 3157      The Kilian Corporation                                          13.0000        1,664.00        1,664.00

    50800105  REINFORCEMENT BARS                      31,140.000    POUND
 0338      Baxmeyer Construction, Inc.                                      1.1000       34,254.00       34,254.00
 3085      Keeley & Sons, Inc.                                              1.3500       42,039.00       42,039.00
 3108      Keller Construction, Inc.                                        0.0100          311.40          311.40
 4757      Plocher Construction Company, Inc.                               1.0800       33,631.20       33,631.20
 4928      RCS Construction, Inc.                                           1.0000       31,140.00       31,140.00
 5802      Stutz Excavating, Inc.                                           1.1000       34,254.00       34,254.00
 3157      The Kilian Corporation                                           1.2500       38,925.00       38,925.00

    51500100  NAME PLATES                                  1.000     EACH
 0338      Baxmeyer Construction, Inc.                                    510.0000          510.00          510.00
 3085      Keeley & Sons, Inc.                                            575.0000          575.00          575.00
 3108      Keller Construction, Inc.                                      515.0000          515.00          515.00
 4757      Plocher Construction Company, Inc.                             401.3000          401.30          401.30
 4928      RCS Construction, Inc.                                         440.0000          440.00          440.00
 5802      Stutz Excavating, Inc.                                         500.0000          500.00          500.00
 3157      The Kilian Corporation                                         475.0000          475.00          475.00

    52200105  FUR SOLDIER PILES WS                       303.000     FOOT
 0338      Baxmeyer Construction, Inc.                                     65.0000       19,695.00       19,695.00
 3085      Keeley & Sons, Inc.                                             43.8000       13,271.40       13,271.40
 3108      Keller Construction, Inc.                                       51.8700       15,716.61       15,716.61
 4757      Plocher Construction Company, Inc.                              50.0000       15,150.00       15,150.00
 4928      RCS Construction, Inc.                                          47.0000       14,241.00       14,241.00
 5802      Stutz Excavating, Inc.                                          44.5000       13,483.50       13,483.50
 3157      The Kilian Corporation                                         130.0000       39,390.00       39,390.00

    52200200  DRILL SET SLD PI SOIL                      962.000    CU FT
 0338      Baxmeyer Construction, Inc.                                     39.5000       37,999.00       37,999.00
 3085      Keeley & Sons, Inc.                                             27.8000       26,743.60       26,743.60
 3108      Keller Construction, Inc.                                       50.7000       48,773.40       48,773.40
 4757      Plocher Construction Company, Inc.                              49.0000       47,138.00       47,138.00
 4928      RCS Construction, Inc.                                          45.5000       43,771.00       43,771.00
 5802      Stutz Excavating, Inc.                                          82.0000       78,884.00       78,884.00
 3157      The Kilian Corporation                                          30.0000       28,860.00       28,860.00

    52200250  UNTREATED TIMBER LAG                       402.000    SQ FT
 0338      Baxmeyer Construction, Inc.                                     12.5000        5,025.00        5,025.00
 3085      Keeley & Sons, Inc.                                             43.9000       17,647.80       17,647.80
 3108      Keller Construction, Inc.                                       18.5000        7,437.00        7,437.00
 4757      Plocher Construction Company, Inc.                              19.5000        7,839.00        7,839.00
 4928      RCS Construction, Inc.                                          10.0000        4,020.00        4,020.00
 5802      Stutz Excavating, Inc.                                          14.8500        5,969.70        5,969.70
 3157      The Kilian Corporation                                          38.0000       15,276.00       15,276.00

    54003000  CONC BOX CUL                               150.700    CU YD
 0338      Baxmeyer Construction, Inc.                                    880.0000      132,616.00      132,616.00
 3085      Keeley & Sons, Inc.                                            747.6000      112,663.32      112,663.32
 3108      Keller Construction, Inc.                                      867.4400      130,723.21      130,723.21
 4757      Plocher Construction Company, Inc.                           1,100.0000      165,770.00      165,770.00
 4928      RCS Construction, Inc.                                         765.0000      115,285.50      115,285.50
 5802      Stutz Excavating, Inc.                                         975.0000      146,932.50      146,932.50
 3157      The Kilian Corporation                                       1,050.0000      158,235.00      158,235.00

    542A1063  P CUL CL A 2    18                         115.000     FOOT
 0338      Baxmeyer Construction, Inc.                                     42.0000        4,830.00        4,830.00
 3085      Keeley & Sons, Inc.                                             75.0000        8,625.00        8,625.00
 3108      Keller Construction, Inc.                                       46.5000        5,347.50        5,347.50
 4757      Plocher Construction Company, Inc.                              80.0000        9,200.00        9,200.00
 4928      RCS Construction, Inc.                                          75.0000        8,625.00        8,625.00
 5802      Stutz Excavating, Inc.                                          54.9000        6,313.50        6,313.50
 3157      The Kilian Corporation                                          66.0000        7,590.00        7,590.00

    54213453  END SECTIONS 18                              2.000     EACH
 0338      Baxmeyer Construction, Inc.                                    150.0000          300.00          300.00
 3085      Keeley & Sons, Inc.                                            500.0000        1,000.00        1,000.00
 3108      Keller Construction, Inc.                                      727.8300        1,455.66        1,455.66
 4757      Plocher Construction Company, Inc.                             600.0000        1,200.00        1,200.00
 4928      RCS Construction, Inc.                                         935.0000        1,870.00        1,870.00
 5802      Stutz Excavating, Inc.                                         430.0000          860.00          860.00
 3157      The Kilian Corporation                                         710.0000        1,420.00        1,420.00

    59100100  GEOCOMPOSITE WALL DR                        13.000    SQ YD
 0338      Baxmeyer Construction, Inc.                                     32.0000          416.00          416.00
 3085      Keeley & Sons, Inc.                                             83.9000        1,090.70        1,090.70
 3108      Keller Construction, Inc.                                       45.3800          589.94          589.94
 4757      Plocher Construction Company, Inc.                              56.0000          728.00          728.00
 4928      RCS Construction, Inc.                                          25.0000          325.00          325.00
 5802      Stutz Excavating, Inc.                                          21.0000          273.00          273.00
 3157      The Kilian Corporation                                          51.0000          663.00          663.00

    60206600  CB TB T7G                                    2.000     EACH
 0338      Baxmeyer Construction, Inc.                                  2,950.0000        5,900.00        5,900.00
 3085      Keeley & Sons, Inc.                                          2,765.0000        5,530.00        5,530.00
 3108      Keller Construction, Inc.                                    4,120.0000        8,240.00        8,240.00
 4757      Plocher Construction Company, Inc.                           4,500.0000        9,000.00        9,000.00
 4928      RCS Construction, Inc.                                       3,575.0000        7,150.00        7,150.00
 5802      Stutz Excavating, Inc.                                       2,820.0000        5,640.00        5,640.00
 3157      The Kilian Corporation                                       3,850.0000        7,700.00        7,700.00

    63000001  SPBGR TY A  6FT POSTS                      412.500     FOOT
 0338      Baxmeyer Construction, Inc.                                     23.7500        9,796.88        9,796.88
 3085      Keeley & Sons, Inc.                                             22.9000        9,446.25        9,446.25
 3108      Keller Construction, Inc.                                       24.4000       10,065.00       10,065.00
 4757      Plocher Construction Company, Inc.                              23.0000        9,487.50        9,487.50
 4928      RCS Construction, Inc.                                          27.0000       11,137.50       11,137.50
 5802      Stutz Excavating, Inc.                                          25.6000       10,560.00       10,560.00
 3157      The Kilian Corporation                                          25.0000       10,312.50       10,312.50

    63000030  SPGR ATT TO CULVERT                         50.000     FOOT
 0338      Baxmeyer Construction, Inc.                                    261.0000       13,050.00       13,050.00
 3085      Keeley & Sons, Inc.                                            251.4100       12,570.50       12,570.50
 3108      Keller Construction, Inc.                                      176.2500        8,812.50        8,812.50
 4757      Plocher Construction Company, Inc.                             235.0000       11,750.00       11,750.00
 4928      RCS Construction, Inc.                                         125.0000        6,250.00        6,250.00
 5802      Stutz Excavating, Inc.                                         220.0000       11,000.00       11,000.00
 3157      The Kilian Corporation                                         117.0000        5,850.00        5,850.00

    63100167  TR BAR TRM T1 SPL TAN                        4.000     EACH
 0338      Baxmeyer Construction, Inc.                                  2,990.0000       11,960.00       11,960.00
 3085      Keeley & Sons, Inc.                                          2,879.4600       11,517.84       11,517.84
 3108      Keller Construction, Inc.                                    3,050.0000       12,200.00       12,200.00
 4757      Plocher Construction Company, Inc.                           2,800.0000       11,200.00       11,200.00
 4928      RCS Construction, Inc.                                       3,350.0000       13,400.00       13,400.00
 5802      Stutz Excavating, Inc.                                       3,200.0000       12,800.00       12,800.00
 3157      The Kilian Corporation                                       3,150.0000       12,600.00       12,600.00

    63200310  GUARDRAIL REMOV                            671.000     FOOT
 0338      Baxmeyer Construction, Inc.                                      4.0000        2,684.00        2,684.00
 3085      Keeley & Sons, Inc.                                              6.2800        4,213.88        4,213.88
 3108      Keller Construction, Inc.                                        3.1600        2,120.36        2,120.36
 4757      Plocher Construction Company, Inc.                               3.1300        2,100.23        2,100.23
 4928      RCS Construction, Inc.                                           3.5000        2,348.50        2,348.50
 5802      Stutz Excavating, Inc.                                           5.5000        3,690.50        3,690.50
 3157      The Kilian Corporation                                           5.5000        3,690.50        3,690.50

    63500105  DELINEATORS                                  2.000     EACH
 0338      Baxmeyer Construction, Inc.                                    106.0000          212.00          212.00
 3085      Keeley & Sons, Inc.                                            204.0000          408.00          408.00
 3108      Keller Construction, Inc.                                       75.0000          150.00          150.00
 4757      Plocher Construction Company, Inc.                             100.0000          200.00          200.00
 4928      RCS Construction, Inc.                                          82.5000          165.00          165.00
 5802      Stutz Excavating, Inc.                                          78.7500          157.50          157.50
 3157      The Kilian Corporation                                          76.0000          152.00          152.00

    64200108  SHOULDER RUM STRIP  8                    1,080.000     FOOT
 0338      Baxmeyer Construction, Inc.                                      7.5000        8,100.00        8,100.00
 3085      Keeley & Sons, Inc.                                              6.6300        7,160.40        7,160.40
 3108      Keller Construction, Inc.                                        6.0000        6,480.00        6,480.00
 4757      Plocher Construction Company, Inc.                               8.0500        8,694.00        8,694.00
 4928      RCS Construction, Inc.                                           9.0000        9,720.00        9,720.00
 5802      Stutz Excavating, Inc.                                           3.6000        3,888.00        3,888.00
 3157      The Kilian Corporation                                           5.0000        5,400.00        5,400.00

    66600105  FUR ERECT ROW MARKERS                        5.000     EACH
 0338      Baxmeyer Construction, Inc.                                    163.0000          815.00          815.00
 3085      Keeley & Sons, Inc.                                            168.3000          841.50          841.50
 3108      Keller Construction, Inc.                                      220.0000        1,100.00        1,100.00
 4757      Plocher Construction Company, Inc.                             220.0000        1,100.00        1,100.00
 4928      RCS Construction, Inc.                                         181.5000          907.50          907.50
 5802      Stutz Excavating, Inc.                                         230.0000        1,150.00        1,150.00
 3157      The Kilian Corporation                                         400.0000        2,000.00        2,000.00

    67000400  ENGR FIELD OFFICE A                          4.000   CAL MO
 0338      Baxmeyer Construction, Inc.                                  1,500.0000        6,000.00        6,000.00
 3085      Keeley & Sons, Inc.                                          2,980.0000       11,920.00       11,920.00
 3108      Keller Construction, Inc.                                    1,430.0000        5,720.00        5,720.00
 4757      Plocher Construction Company, Inc.                             650.0000        2,600.00        2,600.00
 4928      RCS Construction, Inc.                                       1,650.0000        6,600.00        6,600.00
 5802      Stutz Excavating, Inc.                                       1,800.0000        7,200.00        7,200.00
 3157      The Kilian Corporation                                       1,900.0000        7,600.00        7,600.00

    67100100  MOBILIZATION                                 1.000    L SUM
 0338      Baxmeyer Construction, Inc.                                 26,279.1200       26,279.12       26,279.12
 3085      Keeley & Sons, Inc.                                         40,000.0000       40,000.00       40,000.00
 3108      Keller Construction, Inc.                                   72,800.0000       72,800.00       72,800.00
 4757      Plocher Construction Company, Inc.                          57,400.0000       57,400.00       57,400.00
 4928      RCS Construction, Inc.                                      46,000.0000       46,000.00       46,000.00
 5802      Stutz Excavating, Inc.                                      37,000.0000       37,000.00       37,000.00
 3157      The Kilian Corporation                                      41,065.0000       41,065.00       41,065.00

    70101830  TRAF CONT-PROT BLR 21                        1.000    L SUM
 0338      Baxmeyer Construction, Inc.                                  1,700.0000        1,700.00        1,700.00
 3085      Keeley & Sons, Inc.                                          2,890.0000        2,890.00        2,890.00
 3108      Keller Construction, Inc.                                    1,600.0000        1,600.00        1,600.00
 4757      Plocher Construction Company, Inc.                           2,500.0000        2,500.00        2,500.00
 4928      RCS Construction, Inc.                                       1,750.0000        1,750.00        1,750.00
 5802      Stutz Excavating, Inc.                                       1,680.0000        1,680.00        1,680.00
 3157      The Kilian Corporation                                       2,500.0000        2,500.00        2,500.00

    70107025  CHANGEABLE MESSAGE SN                      600.000   CAL DA
 0338      Baxmeyer Construction, Inc.                                     37.1500       22,290.00       22,290.00
 3085      Keeley & Sons, Inc.                                             38.9200       23,352.00       23,352.00
 3108      Keller Construction, Inc.                                       37.1500       22,290.00       22,290.00
 4757      Plocher Construction Company, Inc.                              40.0000       24,000.00       24,000.00
 4928      RCS Construction, Inc.                                          41.0000       24,600.00       24,600.00
 5802      Stutz Excavating, Inc.                                          39.0000       23,400.00       23,400.00
 3157      The Kilian Corporation                                          38.0000       22,800.00       22,800.00

    70300100  SHORT TERM PAVT MKING                       54.000     FOOT
 0338      Baxmeyer Construction, Inc.                                      0.0100            0.54            0.54
 3085      Keeley & Sons, Inc.                                              1.1400           61.56           61.56
 3108      Keller Construction, Inc.                                        1.1100           59.94           59.94
 4757      Plocher Construction Company, Inc.                               1.1100           59.94           59.94
 4928      RCS Construction, Inc.                                           1.2500           67.50           67.50
 5802      Stutz Excavating, Inc.                                           3.0000          162.00          162.00
 3157      The Kilian Corporation                                           0.0100            0.54            0.54

    70300150  SHRT TRM PAVT MK REM                        18.000    SQ FT
 0338      Baxmeyer Construction, Inc.                                      0.0100            0.18            0.18
 3085      Keeley & Sons, Inc.                                             15.0000          270.00          270.00
 3108      Keller Construction, Inc.                                        2.0000           36.00           36.00
 4757      Plocher Construction Company, Inc.                              20.0000          360.00          360.00
 4928      RCS Construction, Inc.                                          12.2500          220.50          220.50
 5802      Stutz Excavating, Inc.                                          12.0000          216.00          216.00
 3157      The Kilian Corporation                                           0.0100            0.18            0.18

    70300220  TEMP PVT MK LINE 4                       1,867.000     FOOT
 0338      Baxmeyer Construction, Inc.                                      0.0100           18.67           18.67
 3085      Keeley & Sons, Inc.                                              0.8200        1,530.94        1,530.94
 3108      Keller Construction, Inc.                                        0.0100           18.67           18.67
 4757      Plocher Construction Company, Inc.                               0.8000        1,493.60        1,493.60
 4928      RCS Construction, Inc.                                           1.0000        1,867.00        1,867.00
 5802      Stutz Excavating, Inc.                                           0.0100           18.67           18.67
 3157      The Kilian Corporation                                           0.0100           18.67           18.67

    72000100  SIGN PANEL T1                               20.000    SQ FT
 0338      Baxmeyer Construction, Inc.                                     23.0000          460.00          460.00
 3085      Keeley & Sons, Inc.                                             32.6400          652.80          652.80
 3108      Keller Construction, Inc.                                       22.0000          440.00          440.00
 4757      Plocher Construction Company, Inc.                              22.0000          440.00          440.00
 4928      RCS Construction, Inc.                                          35.0000          700.00          700.00
 5802      Stutz Excavating, Inc.                                          23.0000          460.00          460.00
 3157      The Kilian Corporation                                          23.0000          460.00          460.00

    72400100  REMOV SIN PAN ASSY TA                        1.000     EACH
 0338      Baxmeyer Construction, Inc.                                     97.0000           97.00           97.00
 3085      Keeley & Sons, Inc.                                            290.0000          290.00          290.00
 3108      Keller Construction, Inc.                                       25.0000           25.00           25.00
 4757      Plocher Construction Company, Inc.                              70.0000           70.00           70.00
 4928      RCS Construction, Inc.                                          93.5000           93.50           93.50
 5802      Stutz Excavating, Inc.                                          90.0000           90.00           90.00
 3157      The Kilian Corporation                                          80.0000           80.00           80.00

    72400310  REMOV SIGN PANEL T1                         18.000    SQ FT
 0338      Baxmeyer Construction, Inc.                                     10.7500          193.50          193.50
 3085      Keeley & Sons, Inc.                                             37.9000          682.20          682.20
 3108      Keller Construction, Inc.                                        5.0000           90.00           90.00
 4757      Plocher Construction Company, Inc.                               4.0000           72.00           72.00
 4928      RCS Construction, Inc.                                           5.0000           90.00           90.00
 5802      Stutz Excavating, Inc.                                           5.0000           90.00           90.00
 3157      The Kilian Corporation                                          18.0000          324.00          324.00

    72501000  TERMINAL MARKER - DA                         4.000     EACH
 0338      Baxmeyer Construction, Inc.                                     28.5000          114.00          114.00
 3085      Keeley & Sons, Inc.                                             27.5400          110.16          110.16
 3108      Keller Construction, Inc.                                       40.0000          160.00          160.00
 4757      Plocher Construction Company, Inc.                              45.0000          180.00          180.00
 4928      RCS Construction, Inc.                                          44.0000          176.00          176.00
 5802      Stutz Excavating, Inc.                                          42.0000          168.00          168.00
 3157      The Kilian Corporation                                          41.0000          164.00          164.00

    72900100  METAL POST TY A                             10.000     FOOT
 0338      Baxmeyer Construction, Inc.                                     13.2500          132.50          132.50
 3085      Keeley & Sons, Inc.                                             20.4000          204.00          204.00
 3108      Keller Construction, Inc.                                       12.5000          125.00          125.00
 4757      Plocher Construction Company, Inc.                              12.5000          125.00          125.00
 4928      RCS Construction, Inc.                                          22.0000          220.00          220.00
 5802      Stutz Excavating, Inc.                                          13.0000          130.00          130.00
 3157      The Kilian Corporation                                          13.0000          130.00          130.00

    73000100  WOOD SIN SUPPORT                            50.000     FOOT
 0338      Baxmeyer Construction, Inc.                                     30.2500        1,512.50        1,512.50
 3085      Keeley & Sons, Inc.                                             25.5000        1,275.00        1,275.00
 3108      Keller Construction, Inc.                                       28.5000        1,425.00        1,425.00
 4757      Plocher Construction Company, Inc.                              28.5000        1,425.00        1,425.00
 4928      RCS Construction, Inc.                                          27.5000        1,375.00        1,375.00
 5802      Stutz Excavating, Inc.                                          30.0000        1,500.00        1,500.00
 3157      The Kilian Corporation                                          29.0000        1,450.00        1,450.00

    78000200  THPL PVT MK LINE  4                      1,867.000     FOOT
 0338      Baxmeyer Construction, Inc.                                      1.0000        1,867.00        1,867.00
 3085      Keeley & Sons, Inc.                                              0.9000        1,680.30        1,680.30
 3108      Keller Construction, Inc.                                        0.8800        1,642.96        1,642.96
 4757      Plocher Construction Company, Inc.                               0.8800        1,642.96        1,642.96
 4928      RCS Construction, Inc.                                           2.0000        3,734.00        3,734.00
 5802      Stutz Excavating, Inc.                                           1.9500        3,640.65        3,640.65
 3157      The Kilian Corporation                                           1.9000        3,547.30        3,547.30

    78100100  RAISED REFL PAVT MKR                         8.000     EACH
 0338      Baxmeyer Construction, Inc.                                     91.0000          728.00          728.00
 3085      Keeley & Sons, Inc.                                             87.2000          697.60          697.60
 3108      Keller Construction, Inc.                                       85.5000          684.00          684.00
 4757      Plocher Construction Company, Inc.                              85.5000          684.00          684.00
 4928      RCS Construction, Inc.                                          89.0000          712.00          712.00
 5802      Stutz Excavating, Inc.                                          85.0000          680.00          680.00
 3157      The Kilian Corporation                                          83.0000          664.00          664.00

    78200006  GRDRAIL REF TYPE B                          10.000     EACH
 0338      Baxmeyer Construction, Inc.                                     13.2500          132.50          132.50
 3085      Keeley & Sons, Inc.                                             12.7500          127.50          127.50
 3108      Keller Construction, Inc.                                        9.7500           97.50           97.50
 4757      Plocher Construction Company, Inc.                               8.0000           80.00           80.00
 4928      RCS Construction, Inc.                                          10.7500          107.50          107.50
 5802      Stutz Excavating, Inc.                                          10.2500          102.50          102.50
 3157      The Kilian Corporation                                          10.0000          100.00          100.00

    78300200  RAISED REF PVT MK REM                        8.000     EACH
 0338      Baxmeyer Construction, Inc.                                     18.2500          146.00          146.00
 3085      Keeley & Sons, Inc.                                              8.1600           65.28           65.28
 3108      Keller Construction, Inc.                                       10.0000           80.00           80.00
 4757      Plocher Construction Company, Inc.                              17.2200          137.76          137.76
 4928      RCS Construction, Inc.                                          19.0000          152.00          152.00
 5802      Stutz Excavating, Inc.                                          25.0000          200.00          200.00
 3157      The Kilian Corporation                                          10.0000           80.00           80.00