                                               ILLINOIS DEPARTMENT OF TRANSPORTATION                                      PAGE:    1
 01/08/24  08:59:58                   U N I T  P R I C E   T A B U L A T I O N   O F   B I D S
 LETTING DATE: 11/17/2023  LETTING TYPE: SCHEDULED                                 CONTRACT NUMBER: 72H57  LETTING ITEM NUMBER: 066
 RESPONSIBLE DISTRICT: 06                                                                                  BIDS LOCKED: Y
 SECTION: (22B)BDR,BJR1,BRR1                       COUNTY: HANCOCK                                         ESTIMATE:
                                                      --------------------------
                                                      SUMMARY OF CONTRACTOR BIDS
                                                      --------------------------

                                                             "AS READ"          SUMMATION    SUMMATION OF                       NBR
 BIDR                     CONTR        COMB  ITEM  CONTR      BIDDER            OF BIDDER     CALCULATED   LOW   BIDR CALC      BLANK
 NBR   BIDDER NAME        GROUP  COMB  GRP   NBR   GROUP      TOTAL PRICE       EXTENSIONS    EXTENSIONS   BID   EXTENSION DIFF BIDS


 1908  Freesen, a div of UCM, Inc.
                          NO ALT                            8,876,669.71 *   8,876,669.71   8,876,669.71    *

 5310  Sangamo Construction Company
                          NO ALT                           10,152,945.79    10,152,945.79  10,152,945.79

 **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT =      53
                                                       ----------------------
                                                       DETAIL CONTRACTOR BIDS
                                                       ----------------------

    ITEM NBR  ITEM DESCRIPTION                                    UNIT OF     UNIT        BIDDER         CALCULATED  BIDR CALC
 BIDR NBR  BIDDER NAME                                  QUANTITY  MEASURE     PRICE       EXTENSION      EXTENSION   EXTENSION DIFF


    X0327739  MISC ELECTRICAL WORK                         1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                 26,388.1400       26,388.14       26,388.14
 5310      Sangamo Construction Company                                15,605.7200       15,605.72       15,605.72

    X4403300  CONC MEDIAN REMOV                        1,185.000    SQ FT
 1908      Freesen, a div of UCM, Inc.                                      4.8000        5,688.00        5,688.00
 5310      Sangamo Construction Company                                    16.6400       19,718.40       19,718.40

    X5030250  BR DECK GROOVING LONG                   17,813.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     14.1800      252,588.34      252,588.34
 5310      Sangamo Construction Company                                    15.7500      280,554.75      280,554.75

    X6024503  INLET ADJ NEW F&G SPL                        1.000     EACH
 1908      Freesen, a div of UCM, Inc.                                  8,956.6800        8,956.68        8,956.68
 5310      Sangamo Construction Company                                 4,238.0100        4,238.01        4,238.01

    X6061702  CONC MED TSM DOW                         1,381.000    SQ FT
 1908      Freesen, a div of UCM, Inc.                                     18.8900       26,087.09       26,087.09
 5310      Sangamo Construction Company                                    41.0100       56,634.81       56,634.81

    X6430130  REM IMP ATTEN SO                             1.000     EACH
 1908      Freesen, a div of UCM, Inc.                                  1,869.0900        1,869.09        1,869.09
 5310      Sangamo Construction Company                                 4,972.1700        4,972.17        4,972.17

    X7010214  TC-PROT 701431 SPL                           1.000     EACH
 1908      Freesen, a div of UCM, Inc.                                143,766.3700      143,766.37      143,766.37
 5310      Sangamo Construction Company                               206,849.4000      206,849.40      206,849.40

    X7011801  TRAF CONT-PROT BLR 22                        1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                 13,475.0000       13,475.00       13,475.00
 5310      Sangamo Construction Company                                22,597.4000       22,597.40       22,597.40

    X7040012  TEMP CON BAR (PERM)                        312.000     FOOT
 1908      Freesen, a div of UCM, Inc.                                    122.1000       38,095.20       38,095.20
 5310      Sangamo Construction Company                                   134.5000       41,964.00       41,964.00

    X7200201  WIDTH RESTRICT SIGN                          1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                  6,655.0000        6,655.00        6,655.00
 5310      Sangamo Construction Company                                 6,773.1600        6,773.16        6,773.16

    Z0001906  STRUCT STEEL REPAIR                          1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                 37,145.6500       37,145.65       37,145.65
 5310      Sangamo Construction Company                                25,344.3700       25,344.37       25,344.37

    Z0012136  BR DECK SCAR    1 1/2                    5,170.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     56.7700      293,500.90      293,500.90
 5310      Sangamo Construction Company                                    52.6800      272,355.60      272,355.60

    Z0012138  BR DECK SCAR    1 3/4                   17,620.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     55.0800      970,509.60      970,509.60
 5310      Sangamo Construction Company                                    53.6400      945,136.80      945,136.80

    Z0012166  BR DK MIC C OVL 2 3/4                   22,790.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                    131.0700    2,987,085.30    2,987,085.30
 5310      Sangamo Construction Company                                   133.6000    3,044,744.00    3,044,744.00

    Z0013798  CONSTRUCTION LAYOUT                          1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                 27,500.0000       27,500.00       27,500.00
 5310      Sangamo Construction Company                                89,522.4900       89,522.49       89,522.49

    Z0016001  DECK SLAB REP (FD-T1)                       10.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                  3,352.9200       33,529.20       33,529.20
 5310      Sangamo Construction Company                                 8,886.8700       88,868.70       88,868.70

    Z0018051  DRAINAGE SCUPPERS ADJ                       10.000     EACH
 1908      Freesen, a div of UCM, Inc.                                  1,530.5800       15,305.80       15,305.80
 5310      Sangamo Construction Company                                 2,998.1400       29,981.40       29,981.40

    Z0029090  DIAMOND GRIND BR SEC                    23,009.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     18.1200      416,923.08      416,923.08
 5310      Sangamo Construction Company                                    20.6700      475,596.03      475,596.03

    Z0034393  MODULAR EXPAN JT  9                        198.000     FOOT
 1908      Freesen, a div of UCM, Inc.                                  4,102.8400      812,362.32      812,362.32
 5310      Sangamo Construction Company                                 7,834.8500    1,551,300.30    1,551,300.30

    Z0034396  MODULAR EXPAN JT 12                         66.000     FOOT
 1908      Freesen, a div of UCM, Inc.                                  5,289.2000      349,087.20      349,087.20
 5310      Sangamo Construction Company                                 7,935.2600      523,727.16      523,727.16

    Z0038115  PCC SUR REM    1/2                         138.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     39.2300        5,413.74        5,413.74
 5310      Sangamo Construction Company                                    18.5700        2,562.66        2,562.66

    Z0041895  POLYMER CONCRETE                             3.400    CU FT
 1908      Freesen, a div of UCM, Inc.                                  1,335.8800        4,541.99        4,541.99
 5310      Sangamo Construction Company                                 1,285.3100        4,370.05        4,370.05

    Z0048665  RR PROT LIABILITY INS                        1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                 12,657.9700       12,657.97       12,657.97
 5310      Sangamo Construction Company                                 5,333.1900        5,333.19        5,333.19

    Z0076600  TRAINEES                                 2,500.000     HOUR
 1908      Freesen, a div of UCM, Inc.                                      0.8000        2,000.00        2,000.00
 5310      Sangamo Construction Company                                     0.8000        2,000.00        2,000.00

    Z0076604  TRAINEES TPG                             2,500.000     HOUR
 1908      Freesen, a div of UCM, Inc.                                     15.0000       37,500.00       37,500.00
 5310      Sangamo Construction Company                                    15.0000       37,500.00       37,500.00

    31101200  SUB GRAN MAT B  4                          359.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     32.5600       11,689.04       11,689.04
 5310      Sangamo Construction Company                                    28.4300       10,206.37       10,206.37

    35300410  PCC BSE CSE  9 1/2                         211.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                    201.8000       42,579.80       42,579.80
 5310      Sangamo Construction Company                                   125.9500       26,575.45       26,575.45

    35300730  PCC BSE CSE 14 1/4                         148.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                    293.7600       43,476.48       43,476.48
 5310      Sangamo Construction Company                                   165.4600       24,488.08       24,488.08

    40600290  BIT MATLS TACK CT                          495.000    POUND
 1908      Freesen, a div of UCM, Inc.                                      2.6900        1,331.55        1,331.55
 5310      Sangamo Construction Company                                    15.7000        7,771.50        7,771.50

    40600985  PCC SURF REM BUTT JT                       267.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     50.6900       13,534.23       13,534.23
 5310      Sangamo Construction Company                                    21.4200        5,719.14        5,719.14

    40604162  P HMA SC IL-9.5 D N70                      109.000      TON
 1908      Freesen, a div of UCM, Inc.                                    575.3000       62,707.70       62,707.70
 5310      Sangamo Construction Company                                   593.8100       64,725.29       64,725.29

    44000100  PAVEMENT REM                               228.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     76.4200       17,423.76       17,423.76
 5310      Sangamo Construction Company                                    56.2900       12,834.12       12,834.12

    44000155  HMA SURF REM    1 1/2                      694.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                     36.6800       25,455.92       25,455.92
 5310      Sangamo Construction Company                                    18.5700       12,887.58       12,887.58

    44001980  CONC BARRIER REMOV                         312.000     FOOT
 1908      Freesen, a div of UCM, Inc.                                     30.1600        9,409.92        9,409.92
 5310      Sangamo Construction Company                                    29.0800        9,072.96        9,072.96

    50102400  CONC REM                                    73.100    CU YD
 1908      Freesen, a div of UCM, Inc.                                  3,841.7800      280,834.12      280,834.12
 5310      Sangamo Construction Company                                 5,149.5800      376,434.30      376,434.30

    50300255  CONC SUP-STR                                77.200    CU YD
 1908      Freesen, a div of UCM, Inc.                                  7,453.5200      575,411.74      575,411.74
 5310      Sangamo Construction Company                                 6,464.6200      499,068.66      499,068.66

    50300300  PROTECTIVE COAT                         24,865.000    SQ YD
 1908      Freesen, a div of UCM, Inc.                                      3.8900       96,724.85       96,724.85
 5310      Sangamo Construction Company                                     3.2100       79,816.65       79,816.65

    50800205  REINF BARS, EPOXY CTD                   24,210.000    POUND
 1908      Freesen, a div of UCM, Inc.                                      3.5600       86,187.60       86,187.60
 5310      Sangamo Construction Company                                     3.6400       88,124.40       88,124.40

    50800515  BAR SPLICERS                               300.000     EACH
 1908      Freesen, a div of UCM, Inc.                                     78.0400       23,412.00       23,412.00
 5310      Sangamo Construction Company                                     1.0000          300.00          300.00

    50800530  MECHANICAL SPLICERS                      1,976.000     EACH
 1908      Freesen, a div of UCM, Inc.                                     86.3500      170,627.60      170,627.60
 5310      Sangamo Construction Company                                    97.5900      192,837.84      192,837.84

    52000110  PREF JT STRIP SEAL                         132.000     FOOT
 1908      Freesen, a div of UCM, Inc.                                    436.0300       57,555.96       57,555.96
 5310      Sangamo Construction Company                                   330.4900       43,624.68       43,624.68

    59200101  BRIDGE WASHING  N1                           1.000     EACH
 1908      Freesen, a div of UCM, Inc.                                 57,200.0000       57,200.00       57,200.00
 5310      Sangamo Construction Company                                55,465.2200       55,465.22       55,465.22

    64300750  IMP ATTEN SU  NAR TL2                        1.000     EACH
 1908      Freesen, a div of UCM, Inc.                                 38,775.0000       38,775.00       38,775.00
 5310      Sangamo Construction Company                                37,599.0200       37,599.02       37,599.02

    67000400  ENGR FIELD OFFICE A                         12.000   CAL MO
 1908      Freesen, a div of UCM, Inc.                                  3,767.8600       45,214.32       45,214.32
 5310      Sangamo Construction Company                                 3,386.3200       40,635.84       40,635.84

    67100100  MOBILIZATION                                 1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                545,192.8600      545,192.86      545,192.86
 5310      Sangamo Construction Company                               599,023.8000      599,023.80      599,023.80

    70102630  TR CONT & PROT 701601                        1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                 16,775.0000       16,775.00       16,775.00
 5310      Sangamo Construction Company                                66,290.7900       66,290.79       66,290.79

    70102635  TR CONT & PROT 701701                        1.000    L SUM
 1908      Freesen, a div of UCM, Inc.                                  1,155.0000        1,155.00        1,155.00
 5310      Sangamo Construction Company                                 6,609.7400        6,609.74        6,609.74

    70107025  CHANGEABLE MESSAGE SN                      354.000   CAL DA
 1908      Freesen, a div of UCM, Inc.                                     50.0500       17,717.70       17,717.70
 5310      Sangamo Construction Company                                    48.5300       17,179.62       17,179.62

    70600255  IMP ATTN TEMP FRN TL2                        1.000     EACH
 1908      Freesen, a div of UCM, Inc.                                 11,425.0000       11,425.00       11,425.00
 5310      Sangamo Construction Company                                11,148.1500       11,148.15       11,148.15

    78009005  MOD URETH PM LINE  5                    18,146.000     FOOT
 1908      Freesen, a div of UCM, Inc.                                      4.1300       74,942.98       74,942.98
 5310      Sangamo Construction Company                                     4.9300       89,459.78       89,459.78

    78200010  BARR WALL REF TYPE B                       124.000     EACH
 1908      Freesen, a div of UCM, Inc.                                     31.2600        3,876.24        3,876.24
 5310      Sangamo Construction Company                                    19.5400        2,422.96        2,422.96

    78200011  BARR WALL REF TYPE C                       124.000     EACH
 1908      Freesen, a div of UCM, Inc.                                     32.8200        4,069.68        4,069.68
 5310      Sangamo Construction Company                                    19.5400        2,422.96        2,422.96

    78300202  PVT MKG REM WTR BLAST                    2,424.000    SQ FT
 1908      Freesen, a div of UCM, Inc.                                      5.5000       13,332.00       13,332.00
 5310      Sangamo Construction Company                                     4.9300       11,950.32       11,950.32