Region | District | DBE % | VBP % | Federal Project # |
---|---|---|---|---|
3 | 4 | 9.00 | 0.00 | N/A |
County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
---|---|---|---|---|---|
|
|
|
|
|
|
Contract Specifics |
---|
15 Working Days |
No More Contract Specifics |
Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
---|---|---|---|---|---|---|---|
20200100 | CU YD | EARTH EXCAVATION | Base items | 63.000 | |||
20400800 | CU YD | FURNISHED EXCAVATION | Base items | 5.000 | |||
25000200 | ACRE | SEEDING, CLASS 2 | Base items | 0.100 | |||
25000400 | POUND | NITROGEN FERTILIZER NUTRIENT | Base items | 9.000 | |||
25000500 | POUND | PHOSPHORUS FERTILIZER NUTRIENT | Base items | 9.000 | |||
25000600 | POUND | POTASSIUM FERTILIZER NUTRIENT | Base items | 9.000 | |||
25000700 | TON | AGRICULTURAL GROUND LIMESTONE | Base items | 0.200 | |||
25100115 | ACRE | MULCH, METHOD 2 | Base items | 0.100 | |||
28100209 | TON | STONE RIPRAP, CLASS A5 | Base items | 240.000 | |||
28200200 | SQ YD | FILTER FABRIC | Base items | 290.000 | |||
60905305 | FOOT | BOX CULVERTS TO BE CLEANED | Base items | 10.000 | |||
63000003 | FOOT | STEEL PLATE BEAM GUARDRAIL, TYPE A, 9 FOOT POSTS | Base items | 125.000 | |||
63100167 | EACH | TRAFFIC BARRIER TERMINAL, TYPE 1 (SPECIAL) TANGENT | Base items | 2.000 | |||
66500105 | FOOT | WOVEN WIRE FENCE, 4' | Base items | 210.000 | |||
67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
70100450 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701201 | Base items | 1.000 | |||
72501000 | EACH | TERMINAL MARKER - DIRECT APPLIED | Base items | 2.000 | |||
78200005 | EACH | GUARDRAIL REFLECTORS, TYPE A | Base items | 4.000 | |||
X4810200 | CU YD | AGGREGATE SHOULDER REMOVAL | Base items | 15.000 | |||
X5220098 | FOOT | TIMBER RETAINING WALL REMOVAL | Base items | 15.000 | |||
X6650202 | FOOT | WOVEN WIRE FENCE REMOVAL | Base items | 205.000 | |||
Z0001002 | TON | GUARDRAIL AGGREGATE EROSION CONTROL | Base items | 107.000 | |||
Z0013798 | L SUM | CONSTRUCTION LAYOUT | Base items | 1.000 | |||
No More Pay Items |