| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 4 | 7 | 3.00 | 0.00 | 317SBGP111/120 |
| County(s) | IL Project # | Airport | Sponsor | City |
|---|---|---|---|---|
|
DEC 4497 | Decatur | Decatur Park District | Decatur |
| Contract Specifics |
|---|
| The time limit to award this item has been changed from 45 days to 60 days after the scheduled letting. |
| 41 Calendar Days |
| Previously advertised on April 28, 2017 (Item 03A). |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
| AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| AR152411 | L SUM | UNCLASSIFIED EXCAVATION | Base items | 1.000 | |||
| AR152480 | SQ YD | SHOULDER ADJUSTMENT | Base items | 235.000 | |||
| AR152511 | SQ YD | SUBGRADE REPAIR | Base items | 200.000 | |||
| AR152540 | SQ YD | SOIL STABILIZATION FABRIC | Base items | 3,843.000 | |||
| AR156510 | FOOT | SILT FENCE | Base items | 450.000 | |||
| AR209604 | SQ YD | CRUSHED AGG. BASE COURSE - 4" | Base items | 3,843.000 | |||
| AR401900 | SQ YD | REMOVE BITUMINOUS PAVEMENT | Base items | 3,737.000 | |||
| AR501501 | EACH | TEST BATCH PCC CONCRETE | Base items | 1.000 | |||
| AR501506 | SQ YD | 6" PCC PAVEMENT | Base items | 3,795.000 | |||
| AR620520 | SQ FT | PAVEMENT MARKING-WATERBORNE | Base items | 422.000 | |||
| AR620525 | SQ FT | PAVEMENT MARKING-BLACK BORDER | Base items | 428.000 | |||
| AR904510 | SQ YD | SODDING | Base items | 235.000 | |||
| No More Pay Items | |||||||