Bulletin Description

Earthwork and embankment for temporary runaround at the intersection of US 20 and IL 73. US 20: from 0.4 mile west of IL 73 to 1 mile east of IL 73 (Reese Road). IL 73: from 0.4 mile north to 0.2 mile south of US 20.
Region District DBE % VBP % Federal Project #
2 2 3.00 0.00 N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Stephenson
  • FAP 301
  • FAP 654
  • FAS 1087
  • US 20,IL 73
  • (22,107)A
  • C-92-105-25
  • 2-77140-0114
Contract Specifics
Completion Date: October 17, 2025 Plus 5 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (7 Submitted / 7 Answered ) Questions not accepted as of July 22, 2025 04:30 PM.

  • Will the Stabilized Construction Entrances need to be removed in this contract?
    Stabilized construction entrances will remain in place at the end of construction. Special Provision will be added as addendum. (07/23/2025)

  • What is the typical section for the Stabilized Construction Entrance?
    Stabilized construction entrance detail is included within SWPPP. (07/23/2025)

  • In reference to Addendum A, page 5 FURNISH EXCAVATION SPECIAL,5TH PARAGRAPH referring to the below the 4" from final grade will be constructed entirely of Aggregate lime. Is all the embankment below the proposed subgrade of the future pavement to be built with Aggregate lime? If yes will the sides need to be encapsulated with dirt?
    The project should be bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications available online. (07/18/2025)

  • Page 5 of Special provision under Furnish Excavation (Special) under Materials it refers to Furnish Excavation placed below 4" from final grade to be Aggregate Lime please explain what will be required? Application Rate? is it incorporated into what soil? Area to be incorporated into? Contract would be better served if this was added to the Landscaping Pay Items
    The Aggregate Lime is not a soil modification. An Addendum will be issued to further clarify that The FURNISHED EXCAVATION (SPECIAL) placed below 4” from the final graded surface shall be constructed entirely of aggregate lime. (07/10/2025)

  • Can Stockpiled Topsoil be used for the top 4" of vegetation sustaining material as call for in special provision?
    Stockpiled topsoil cannot be used for FURNISHED EXCAVATION (SPECIAL). An addendum will be issued to further clarify that all the material for FURNISHED EXCAVATION (SPECIAL) shall be furnished. (07/10/2025)

  • Notes on plans state Tree Removal to be done after October 1 yet completion date is October 17th????
    The COMMITMENTS Note #1 provides a tree removal restriction window. Contractor must have all work completed by COMPLETION DATE. Contractor must comply with both restrictions. (07/10/2025)

  • For pay Item 5421D024/5422D048 Pipe Culvert CL D TY 1/TY2 24"/48" (Temporary) Special Provisions states Contractor to deliver pipe to State storage yard. wont the removal of Temporary Pipe and delivery of pipe be completed under a future contract and not a part of this contract?
    Pipe culvert (temporary) will be removed in a future contract. An addendum will be issued to correct this special provision. (07/10/2025)

Authorized Bidders

  • 1799 Fischer Excavating, Inc.
    1567 Heine Rd.
    Freeport, IL 61032
    Phone: (815) 233-3232 Fax: (815) 235-7557 Email: tgilbertson@fischerinc.com
    $652,316.75 is within a reasonable approximation of the Estimate

  • 1045 Civil Constructors, Inc. d/b/a/ Helm Civil
    2283 Bus Hwy 20 East
    Freeport, IL 61032
    PO Box 750
    Freeport, IL 61032
    Phone: (815) 235-2200 Fax: (815) 235-2219 Email: civilestimating@helmgroup.com
    $907,317.92

  • 3706 Martin & Company Excavating
    2456 E. Pleasant Grove Road
    Oregon, IL 61061
    P.O. Box 443
    Oregon, IL 61061
    Phone: (815) 732-2422 Fax: (815) 732-2092 Email: info@martincoinc.net
    $760,407.30

  • 4741 Phoenix Corporation of the Quad Cities
    1006 Rosehill Rd
    Port Byron, IL 61275
    PO Box 445
    Rapids City, IL 61278
    Phone: (309) 523-3687 Fax: (309) 523-3752 Email: mdecap@phoenixcorp.org

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
20100110 UNIT TREE REMOVAL (6 TO 15 UNITS DIAMETER) Base items 62.000
20100210 UNIT TREE REMOVAL (OVER 15 UNITS DIAMETER) Base items 83.000
20101000 FOOT TEMPORARY FENCE Base items 547.000
20200100 CU YD EARTH EXCAVATION Base items 2,020.000
21301052 FOOT EXPLORATION TRENCH 52" DEPTH Base items 100.000
25000400 POUND NITROGEN FERTILIZER NUTRIENT Base items 653.000
25000500 POUND PHOSPHORUS FERTILIZER NUTRIENT Base items 653.000
25000600 POUND POTASSIUM FERTILIZER NUTRIENT Base items 653.000
25000750 ACRE MOWING Base items 7.250
25100125 ACRE MULCH, METHOD 3 Base items 5.250
25100630 SQ YD EROSION CONTROL BLANKET Base items 9,483.000
28000250 POUND TEMPORARY EROSION CONTROL SEEDING Base items 725.000
28000305 FOOT TEMPORARY DITCH CHECKS Base items 3,488.000
28000400 FOOT PERIMETER EROSION BARRIER Base items 5,862.000
28000500 EACH INLET AND PIPE PROTECTION Base items 9.000
5421D024 FOOT PIPE CULVERTS, CLASS D, TYPE 1 24" (TEMPORARY) Base items 104.000
5422D048 FOOT PIPE CULVERTS, CLASS D, TYPE 2 48" (TEMPORARY) Base items 460.000
61133100 EACH FIELD TILE JUNCTION VAULTS, 2' DIA. Base items 1.000
61133200 EACH FIELD TILE JUNCTION VAULTS, 3' DIA. Base items 1.000
61133300 EACH FIELD TILE JUNCTION VAULTS, 4' DIA. Base items 1.000
61133400 EACH FIELD TILE JUNCTION VAULTS, 5' DIA. Base items 1.000
61139900 FOOT STORM SEWERS (SPECIAL), 6" Base items 100.000
61140000 FOOT STORM SEWERS (SPECIAL), 8" Base items 100.000
66900200 CU YD NON-SPECIAL WASTE DISPOSAL Base items 10.000
66900530 EACH SOIL DISPOSAL ANALYSIS Base items 1.000
66901001 L SUM REGULATED SUBSTANCES PRE-CONSTRUCTION PLAN Base items 1.000
66901003 L SUM REGULATED SUBSTANCES FINAL CONSTRUCTION REPORT Base items 1.000
66901006 CAL DA REGULATED SUBSTANCES MONITORING Base items 1.000
67000400 CAL MO ENGINEER'S FIELD OFFICE, TYPE A Base items 8.000
67100100 L SUM MOBILIZATION Base items 1.000
70100450 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701201 Base items 1.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 28.000
X0320050 L SUM CONSTRUCTION LAYOUT (SPECIAL) Base items 1.000
X2040805 CU YD FURNISHED EXCAVATION (SPECIAL) Base items 7,540.000
X2111100 CU YD TOPSOIL EXCAVATION AND PLACEMENT (SPECIAL) Base items 11,095.000
X2501845 ACRE SEEDING, CLASS 7 (SPECIAL) Base items 7.250
X7010216 L SUM TRAFFIC CONTROL AND PROTECTION, (SPECIAL) Base items 1.000
Z0013797 SQ YD STABILIZED CONSTRUCTION ENTRANCE Base items 480.000