| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 1 | 1 | 0.00 | 0.00 | N/A |
| County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
|---|---|---|---|---|---|
|
|
|
|
|
|
| Contract Specifics |
|---|
| Small Business Initiative (Bid Bond is not required) |
| 25 Working Days |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| 25003210 | ACRE | INTERSEEDING, CLASS 2A | Base items | 0.500 | |||
| 25100125 | ACRE | MULCH, METHOD 3 | Base items | 0.500 | |||
| 44000400 | FOOT | GUTTER REMOVAL | Base items | 100.000 | |||
| 50300300 | SQ YD | PROTECTIVE COAT | Base items | 28.000 | |||
| 66900200 | CU YD | NON-SPECIAL WASTE DISPOSAL | Base items | 10.000 | |||
| 66900530 | EACH | SOIL DISPOSAL ANALYSIS | Base items | 1.000 | |||
| 66901001 | L SUM | REGULATED SUBSTANCES PRE-CONSTRUCTION PLAN | Base items | 1.000 | |||
| 66901003 | L SUM | REGULATED SUBSTANCES FINAL CONSTRUCTION REPORT | Base items | 1.000 | |||
| 66901006 | CAL DA | REGULATED SUBSTANCES MONITORING | Base items | 2.000 | |||
| 67000400 | CAL MO | ENGINEER'S FIELD OFFICE, TYPE A | Base items | 3.000 | |||
| 67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| 70100310 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701421 | Base items | 1.000 | |||
| X0322906 | EACH | WEEP HOLES CORED | Base items | 124.000 | |||
| X6062400 | FOOT | CONCRETE GUTTER (SPECIAL) | Base items | 100.000 | |||
| Z0015550 | CU YD | DEBRIS REMOVAL | Base items | 22.000 | |||
| Z0018500 | EACH | DRAINAGE STRUCTURES TO BE CLEANED | Base items | 3.000 | |||
| Z0018600 | EACH | DRAINAGE STRUCTURES TO BE RECONSTRUCTED | Base items | 1.000 | |||
| Z0030850 | SQ FT | TEMPORARY INFORMATION SIGNING | Base items | 51.400 | |||
| Z0064800 | UNIT | SELECTIVE CLEARING | Base items | 22.000 | |||
| No More Pay Items | |||||||