Home > Notice of Letting > Contract Detail

September 18, 2026 Letting 12:00 PM
099-78C34

Plans and Special Provisions are not available at this time

Bulletin Description

Tree removal along the east side of I-57 from 3 miles south of the West Frankfort interchange (at mile marker 62) to 3 miles south of the West City interchange (at mile marker 68).
Region District DBE % VBP % Federal Project #
5 9 Pending Pending N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Franklin
  • FAI 57
  • I-57
  • (28,-5-4,-5-3,-5-2,-5-1,-4)TR1
  • C-99-085-26
  • 9-00725-2700
Contract Specifics
Completion Date: March 31, 2027 Plus 10 Working Days
Previously advertised on July 31, 2026 (Item 077).
No More Contract Specifics

Ask Subscribe Questions and Answers (0 Submitted / 0 Answered ) Questions not accepted as of September 08, 2026 04:30 PM.

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
This list of pay items is subject to change until the Plans and Special Provisions have been published.
Pay Item # UOM Description Type Quantity Unit Price
20100110 UNIT TREE REMOVAL (6 TO 15 UNITS DIAMETER) Base items 33,206.000
20100210 UNIT TREE REMOVAL (OVER 15 UNITS DIAMETER) Base items 25,491.000
67100100 L SUM MOBILIZATION Base items 1.000
70100420 EACH TRAFFIC CONTROL AND PROTECTION, STANDARD 701411 Base items 2.000
70100700 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701406 Base items 1.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 28.000
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.